Subject: Change Order to Construction Contract with Angeles Contractor, Inc. for the Sheriff Colorado River Station Remodel Project in Needles
Attachments: 1. CON-PFMD-042324-Change Order to Const Contract w Angeles Contractor, Inc. for the Sheriff Colorado River Station Remodel, 2. Item #40 Executed BAI, 3. 23-929 CO-1 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

April 23, 2024

FROM
DON DAY, Director, Project and Facilities Management Department
SHANNON D. DICUS, Sheriff/Coroner/Public Administrator

SUBJECT
Title
Change Order to Construction Contract with Angeles Contractor, Inc. for the Sheriff Colorado River Station Remodel Project in Needles
End

RECOMMENDATION(S)
Recommendation
Approve Change Order No. 1 to Construction Contract No. 23-929 with Angeles Contractor, Inc., for the Sheriff Colorado River Station Remodel Project in Needles for the Sheriff/Coroner/Public Administrator, in the amount of $373,654, increasing the total contract from $9,115,000 to $9,488,654, with no change to the construction completion date (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional discretionary General Funding (Net County Cost). The Sheriff Colorado River Station Remodel Project (Project) (WBSE 10.10.1220) budget of $13,952,484 is funded with Discretionary General Funding in the amount of $6,594,490 and Proposition 172 funds in the amount of $7,357,994, as approved by the Board of Supervisors as part of the 2023-24 Capital Improvement Program budget.

BACKGROUND INFORMATION
Approval of Change Order No. 1 (CO1), totaling $373,654, with Angeles Contractor, Inc. (Angeles), addresses compensation for necessary additional work not included in the original bid documents for the Project. This includes unanticipated lead abatement for two existing carports, additional costs related to the solar carport, the addition of four tower c...

Click here for full text