Legislation Details

File #: 13702   
Type: Consent Status: Passed
File created: 2/13/2026 Department: Project and Facilities Management
On agenda: 2/24/2026 Final action: 2/24/2026
Subject: Construction Contract with Healthcare Design & Construction, LLC, for the ARMC Telemetry Expansion Project
Attachments: 1. ATT-PFMD-022426 ARMC Telemetry Expansion Construction Contract Addendum 1 Part 2, 2. ATT-PFMD-022426 ARMC Telemetry Expansion Construction Contract Addendum 1 Part 1, 3. R1-CON-PFMD-022426-ARMC Telemetry Expansion Construction Contract, 4. Item #28 Executed BAI, 5. 26-117 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

                                          February 24, 2026

 

FROM

MOE YOUSIF, Interim Director, Project and Facilities Management Department

ANDREW GOLDFRACH, ARMC Chief Executive Officer, Arrowhead Regional Medical Center 

         

SUBJECT                      

Title                     

Construction Contract with Healthcare Design & Construction, LLC, for the ARMC Telemetry Expansion Project

End

 

RECOMMENDATIONS

Recommendation

1.                     Approve Addendum No. 1, dated October 14, 2025, to the bid documents, which provided answers to pre-bid questions, and modified plans and specification documents for the ARMC Telemetry Expansion Project in Colton.

2.                     Award Construction Contract in the amount of $394,869 to Healthcare Design & Construction, LLC, for a contract period of 365 calendar days, from the date of the issuance of the Notice to Proceed, for the ARMC Telemetry Expansion Project in Colton. 

3.                     Authorize the Director of Project and Facilities Management Department to order any necessary changes or additions in the work being performed under the contract, for a total not to exceed $32,243.45 pursuant to Public Contract Code Section 20142.

4.                     Authorize the Director of Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.

(Presenter: Moe Yousif, Interim Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve ARMC County Hospital Operations.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The proposed contract award to Healthcare Design & Construction, LLC in the amount of $394,869 will be funded by the Arrowhead Regional Medical Center (ARMC) Telemetry Expansion project (Project) (WBSE 10.10.1477) budget of $4,715,864. The project is funded by State Medi-Cal, Federal Medicate, Private Insurance reimbursements, and other departmental revenues. Funding sources may change in the future depending on legislative activity related to the repeal or replacement of the Affordable Care Act. Sufficient appropriation and revenue are included in the 2025-26 Capital Improvement Program (CIP) budget as approved by the Board of Supervisors (Board) on June 10, 2025 (Item No. 136).

 

The Project budget of $4,715,864 is comprised of the following components: 

 

Description

Amount

Project Design

$551,927

Project Management, Inspection and Testing

$439,831

Innovation & Technology Department

$50,000

Construction

$2,733,593

Construction Contingency

$    715,948

Start-Up Costs

$    224,565

Total

$ 4,715,864

 

BACKGROUND INFORMATION

The recommended action will award a construction contract to Healthcare Design & Construction, LLC for the ARMC Project which involves the upgrade and expansion of the existing telemetry system throughout the hospital. The scope of work includes installation of seismic anchoring, electrical upgrades, and low voltage systems necessary to support the expanded infrastructure.

 

On June 30, 2025, pursuant to County Policy 11-15, the Assistant Executive Officer determined the Project to be categorically exempt from further review under Section 15301(a) for existing facilities, of the California Environmental Quality Act (CEQA) Guidelines. No further environmental review is required.

 

This project is consistent with Board approved CIP Project No. 24-004.

 

PROCUREMENT

On June 30, 2025, the Assistant Executive Officer, pursuant to County Policy 11-15, authorized the Project and Facilities Management Department (PFMD) to advertise the project for competitive bids. PFMD advertised the project in the San Bernardino Sun, six plan rooms, and the County’s Electronic Procurement Network (ePro) under Request for Proposals No. ANE223-ANE2C-6047 on September 3, 2025. A mandatory job walk was held on September 17, 2025, and was attended by fourteen contractors.

 

Addendum No. 1, dated October 14, 2025, was issued, which provided responses to bidder inquiries and issued ACD 0001, which modified plans and specifications for the Project.

 

On October 29, 2025, the following two bids were received:

 

Name

Location

Bid

Healthcare Design & Construction, LLC

Tustin, CA

$394,869

CDG Builders, Inc.

Irvine, CA

$1,354,713

 

PFMD recommends the Board award the construction contract to Healthcare Design & Construction, LLC, the lowest responsive and responsible bidder.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Daniel Pasek, Deputy County Counsel, 387-5455) December 29, 2025; Arrowhead Regional Medical Center (Andrew Goldfrach, ARMC Chief Executive Officer, 580-6170) on January 13, 2026; Purchasing (Ariel Gill, Supervising Buyer, 387-2070) on January 14, 2026; Project and Facilities Management (Rob Gilliam, Chief of Project Management, 387-5115) on January 14, 2026; and County Finance and Administration (Yael Verduzco, Principal Administrative Analyst, 387-5285) on February 6, 2026.

 

(JR: 387-5000)