Legislation Details

File #: 15050   
Type: Consent Status: Agenda Ready
File created: 10/9/2026 Department: Project and Facilities Management
On agenda: 10/20/2026 Final action:
Subject: Budget Adjustment for Fire Station No. 26 Exterior Staircase and Deck Improvements Project
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

                                          October 20, 2026

 

FROM

MOE YOUSIF, Interim Director, Project and Facilities Management Department

DAN MUNSEY, Fire Chief/Fire Warden, San Bernardino County Fire Protection District

 

SUBJECT                      

Title                     

Budget Adjustment for Fire Station No. 26 Exterior Staircase and Deck Improvements Project

End

 

RECOMMENDATIONS

Recommendation

1.                     Approve a budget increase in the amount of $25,000 to Capital Improvement Program Project No. 25-005, increasing the total project budget from $412,534 to $437,534, for the Fire Station No. 26 Exterior Staircase and Deck Improvements Project located at 737 Grandview Road in Twin Peaks.

2.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post the necessary budget adjustments, as detailed in the Financial Impact section (Four votes required).

(Presenter: Moe Yousif, Interim Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Operate in a Fiscally Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost).

The recommended increase in the amount of $25,000 to the Fire Station No. 26 Exterior Staircase and Deck Improvements Project (Project) (WBSE 10.10.1616), increasing the total project budget from $412,534 to $437,534, will be fully funded by the San Bernardino County Fire Protection District (SBCFPD) Mountain Regional Service Zone Fund. Sufficient appropriation is included in SBCFPD’s 2026-27 budget (Cost Center 6000262448) and will be included in future recommended budgets, if necessary.

 

The Project and Facilities Management Department (PFMD) requests the following adjustments to the 2026-27 budget:

 

Fund Center

Commitment Item

Description

Action

Amount

WBSE

7700003100

54304030

Structures and Improvements to Structures

Increase

$25,000

10.10.1616

7700003100

55415017

Capital Assets Transfers In

Increase

$25,000

10.10.1616

 

BACKGROUND INFORMATION

On June 11, 2024 (Item No. 110), the Board of Supervisors (Board) approved Capital Improvement Program (CIP) Project No. 25-005 in the amount of $412,534. This Project includes the demolition and replacement of the existing 25-year-old exterior staircase and deck. Because the Project involves replacing an aging structure with limited information regarding existing conditions, the design team was required to make assumptions concerning the existing footings, building connections, backing, and structural steel member sizing during the design phase. 

 

Following multiple delays due to mountain region fires, design changes, and coordination with other related projects at Fire Station No. 26, construction of the Project began on May 1, 2026, under the County’s Job Order Contract with SJD&B, Inc. (Contract No. 24-843). As construction progressed, several unforeseen conditions related to the original construction design were also identified, including conditions involving the existing footings, building connections, backing, and structural steel member sizes that must meet minimum building codes. In addition, the original work scope did not fully account for the building code-required third-party special inspections necessary for this type of steel installation. These unforeseen conditions resulted in additional work that was outside the original Project scope and design, necessitating change orders.

 

Additionally, the original Project budget did not account for the level of third-party special inspections required for a structural steel project of this complexity. Pursuant to California Building Code sections 1705, 1705.2, and 1705.3, special inspections are required to verify compliance with the approved plans, project specifications, and applicable building code requirements. Inspections shall include, but are not limited to, concrete placement, grout installation, structural welding, steel construction, concrete construction, and other required structural elements and activities. These inspection services represent a significant project cost that was not fully captured in the original budget.

 

Approval of this budget adjustment will increase the Project budget to complete the unforeseen scope of work, including engineering revisions and associated change orders, as well as code-required third-party special inspections, such as concrete placement, grout installation, structural welding, and other required inspections. This will ensure the structure’s longevity, address safety concerns, and enhance the overall functionality of the space.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Kaleigh Ragon, Deputy County Counsel, 387- 5455) on September 8, 2026; San Bernardino County Fire Protection District (Bertral Washington, Deputy Fire Chief, 387-5974) on September 15, 2026; Auditor-Controller/Treasurer/Tax Collector (Charlene Huang, Auditor-Controller Manager, 382-7022) on September 15, 2026; Project and Facilities Management (Jon Aldana, Interim Chief of Project Management, 387-5115) on September 16, 2026; and County Finance and Administration (Matthew Dalton, Administrative Analyst, 387-5005, and Yael Verduzco, Principal  Administrative Analyst, 387-5285) on October 2, 2026.