Subject: 2023-24 Budget for Board Governed County Service Areas
Attachments: 1. ATT-BGCSA-06-13-23-2023-24 ATT B Budget for Board Governed County Service Areas, 2. RES-BGCSA-06-13-23-2023-24 Budget for Board Governed County Service Areas, 3. ATT-BGCSA-06-13-22-2023-24 ATT A Budget for Board Governed County Service Areas, 4. Item #102 Executed BAI, 5. 2023-84 Executed Resolution

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF BOARD GOVERNED COUNTY SERVICE AREAS

AND RECORD OF ACTION

 

                                          June 13, 2023

 

FROM

LEONARD X. HERNANDEZ, Chief Executive Office, County Administrative Office

         

SUBJECT                      

Title                     

2023-24 Budget for Board Governed County Service Areas

End

 

RECOMMENDATION(S)

Recommendation

Acting as the governing body of the Board Governed County Service Areas:

1.                     Conduct a public hearing on the 2023-24 Recommended Budget for the Board Governed County Service Areas.

2.                     Adopt Resolution to approve and adopt:

a.                     The 2023-24 Budget for the Board Governed County Service Areas, including appropriation, operating transfers out, contribution to reserves/net position, available reserves, estimated net position available and budgeted staffing, and authorization for final fund balance adjustments as described in Attachment A.

b.                     Any changes to the Recommended Budget that the Board of Supervisors may direct.

i.                     In the event that the Board of Supervisors makes any additions or deletions to the budget after the public hearing, and the items were not proposed in writing and filed with the Clerk of the Board of Supervisors before close of the public hearing, a 4/5 vote of the Board of Supervisors is required.

3.                     Approve the establishment of new classifications as detailed in Attachment B.

(Presenter: Matthew Erickson, County Chief Financial Officer, 387-5423)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Promote the Countywide Vision.

Operate in a Fiscally-Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost).

The 2023-24 Recommended Budget for the Board Governed County Service Areas (CSA), as presented in the Recommended Budget Book, includes total requirements of $88.2 million (excluding contributions to reserves/net position) and budgeted staffing of 119 positions for the CSA Operating and Capital Improvement Program (CIP) Funds. 

 

BACKGROUND INFORMATION

The Department of Public Works - Special Districts manages and maintains the Board Governed CSAs that provide a number of municipal services for various communities within San Bernardino County.  These services include television translators, dam maintenance, landscaping, detention basins, open space, park and recreation, road services (including paving, maintenance, and snow removal), streetlights, refuse, sanitation, and water.  In addition, the Department of Airports oversees CSA 60 for the operation and maintenance of Apple Valley Airport.

 

As presented in the Recommended Budget Book, the summary of the CSA 2023-24 Recommended Budget below includes the base amount and any new items for 2023-24.  

 

 Budget Unit

2022-23 Modified Budget

2023-24 Recommended Budget

Change

Requirements

 

 

 

Operating Funds:

 

 

 

General Districts

$12,729,549

$9,556,218

$ (3,173,331)

Park Districts

$3,995,901

$4,926,822

$930,921

Road Districts

$3,942,765

$4,139,529

$196,764

Streetlight Districts

$1,455,055

$2,173,455

$718,400

CSA 60 Apple Valley Airport

$11,970,847

$13,269,769

$1,298,922

CSA 70 HL Havasu Lake

$106,000

$108,130

$2,130

Sanitation Districts

$7,163,445

$8,178,952

$1,015,507

Water Districts

$8,062,394

$10,063,751

$2,001,357

Total Operating Funds

$49,425,956

$52,416,626

$2,990,670

 

 

 

 

CIP Funds:

 

 

 

General Districts

$2,467,108

$15,952,026

$13,484,918

Road Districts

$3,000,000

$300,000

$ (2,700,000)

CSA 60 Apple Valley Airport

$9,197,107

$10,651,334

$1,454,227

Sanitation Districts

$4,433,708

$2,260,925

$ (2,172,783) 

Water Districts

$12,179,372

$6,596,313

$ (5,583,059)

Total CIP Funds

$31,277,295

$35,760,598

$4,483,303

 

 

 

 

Total Requirements

$80,703,251

$88,177,224

$7,473,973

 

 

 

 

Budgeted Staffing

 

 

 

Operations:

 

 

 

General Districts

102

103

1

Park Districts

14

15

1

Road Districts

1

1

0

Total Budgeted Staffing

117

119

2

 Note: Requirements exclude contributions to reserves/net position of $65,905.

 

Budgeted Requirements of $52.4 million for the Operating Funds reflect a net increase of $3 million from the prior fiscal year.  This increase is primarily for the costs to maintain service, including an additional $793,500 in appropriation for the replacement of various equipment and vehicles.

 

Requirements of $35.8 million for the CIP Funds include the projected cost of several CIP projects budgeted in 2023-24.  The most significant of these projects ($500,000 or more) are as follows:

                     American Rescue Plan Act (ARPA) funded projects:

o                     Bohnert/Banyan Sewer Project, which is currently on hold ($8 million)

o                     Glen Helen Waterline Interconnection Project ($1.8 million)

o                     Lake Gregory Regional Park Sediment Management - Phase 1 ($1.7 million)

o                     Glen Helen Lighting Project ($1.6 million)

o                     Kessler Park and Ayala Park Wi-Fi Project in Bloomington ($518,576)

                     CSA 60 Apple Valley Airport:

o                     Perimeter Fence Replacement ($2.9 million)

o                     Airport Café Exterior Patio Structure Renovation ($1.7 million)

o                     Terminal Parking Lot Pavement and Drainage ($1.6 million)

o                     Taxiway Reconstruction and Drainage ($1.6 million)

o                     Terminal Remodel ($1.5 million)

                     CSA 64 Spring Valley Lake (Sanitation) - Lakeview Lift Station Renovation ($1.2 million)

                     CSA 64 Spring Valley Lake (Water) - Recoat Tank Nos. 2A and 2B ($1.0 million)

                     CSA 70 Countywide:

o                     Lake Gregory Regional Park Sediment Project ($3.2 million)

o                     Lake Gregory Dam Rehabilitation ($953,231)

                     CSA 70 D-1 Lake Arrowhead - Mackay Park Maintenance Building Replacement ($1.0 million)

                     CSA 70 J Oak Hills:

o                     Oak Hills New Well No. 6 ($2.1 million)

o                     Reservoir No. 3A Design and Land Acquisition ($990,000)

 

The total Budgeted Staffing of 119 for 2023-24 includes the following changes:

                     Addition of two new positions:

o                     Project Manager for the increased workload resulting from the addition of several new capital projects funded by ARPA.

o                     Office Assistant II to support certain park districts experiencing service gaps during operating hours.

                     Reclassification of two existing positions to better align each position with its assigned tasks and responsibilities:

o                     Position No. 88788 from Office Assistant II to Office Assistant III.

o                     Position No. 30295 from Parks & Recreation Maintenance Worker II to Parks & Recreation Maintenance Worker III.

 

Recommendation No. 1 conducts the public hearing for the CSA 2023-24 Recommended Budget, as required by Government Code Sections 29080 and 29081.  Prior to adopting the 2023-24 budget for the CSA, a notice was published on May 24 and May 30, 2023, setting the date of the public hearing for the purpose of making a determination regarding the Recommended Budget.  The Recommended Budget documents were made available in the Clerk of Board of Supervisors’ (Board) office on May 23, 2023, for the public, and the public hearing is occurring at least 10 days after the documents were made available.  The notice further sets forth that any member of the public may appear at the hearing and be heard regarding any item in the Recommended Budget or for inclusion of additional items.  All proposals for revisions should be submitted in writing to the Clerk of the Board before the close of the public hearing.

 

The public hearing discusses and implements any direction or changes to the Recommended Budget.  Any requests for increases, decreases, or omission of any item in the budget or inclusion of any additional items shall not be made after the public hearing, unless the items were proposed in writing and filed with the Clerk of the Board before the close of the public hearing or unless approved by the Board by a 4/5 vote.

 

Recommendation No. 2 approves and adopts the 2023-24 budget for the CSAs. Attachment A lists the 2023-24 Recommended Budget for appropriation, operating transfers out, contributions to reserves/net position, available reserves, estimated net position available, and budgeted staffing.

 

Recommendation No. 3 is for approval of new classifications as listed in Attachment B. Attachment B lists new classifications for 2023-24.

 

The Recommended Budget, including Attachments A and B, satisfies the requirements set forth in Government Code section 29089.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by Human Resources (Gina King, Deputy Director, 387-5571) on May 31, 2023; County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on May 19, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635) on May 23, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on May 26, 2023. This item has also been coordinated with the Auditor-Controller/Treasurer/Tax Collector (Vanessa Doyle, Chief Deputy Controller, 382-3195) on May 26, 2023.