File #: 4184   
Type: Consent Status: Passed
File created: 5/10/2021 Department: Public Works-Special Districts
On agenda: 5/18/2021 Final action: 5/18/2021
Subject: Capital Improvement Project for Prado Regional Park Bladder Tank Replacement
Attachments: 1. Item #55 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

May 18, 2021

 

FROM

BEAHTA R. DAVIS, Director, Regional Parks Department

BRENDON BIGGS, Director, Department of Public Works - Special Districts

 

SUBJECT

Title

Capital Improvement Project for Prado Regional Park Bladder Tank Replacement

End

 

RECOMMENDATION(S)

Recommendation

Approve Capital Improvement Program project in the amount of $115,000 for Prado Regional Park Bladder Tank Replacement that will be managed by the Department of Public Works - Special Districts.

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost) as the cost of this project ($115,000) will be funded through an existing Memorandum of Understanding (MOU) between the County of San Bernardino (County) and County Service Area 70 wherein the Department of Public Works - Special Districts (Department) provides preventative maintenance, emergency response, and support services for County-owned water and wastewater systems at all County Regional Parks.  This MOU was approved by the Board of Supervisors (Board) on June 25, 2019 (Item No. 74) and will continue until June 30, 2024. Adequate appropriation and revenue for this project are included in the 2020-21 MOU budget and will be included in the 2021-22 recommended budget since the project will not be completed by fiscal year-end.

 

BACKGROUND INFORMATION

Pursuant to MOU No. 19-449, the Department provides maintenance and repair services for water and sewer facilities at the County’s Regional Parks.  The Prado Regional Park water distribution system has an on-site storage reservoir and a ‘pump on demand’ system for daily normal water usage demands and fire suppression throughout the park. The ‘pump on demand’ system is equipped with two bladder tanks for low flow periods to save energy costs and pump wear. These two bladder tanks have failed and are not repairable. Replacement of these two units is necessary to return the park’s water distribution system to normal designed operations. 

 

PROCUREMENT

Upon Board approval of this item, the Department will proceed with the Prado Regional Park Bladder Tank Replacement project by soliciting competitive bids for replacement of the bladder tanks.

 

 

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Dawn Martin, Deputy County Counsel, 387-5455) on April 26, 2021; Finance (Tom Forster, Administrative Analyst, 387-4635 and Carl Lofton, Administrative Analyst, 387-5404) on April 28, 2021; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on May 2, 2021.