San Bernardino header
File #: 2775   
Type: Consent Status: Passed
File created: 8/17/2020 Department: Real Estate Services-Project Management Division
On agenda: 8/25/2020 Final action: 8/25/2020
Subject: Amendment No. 1 to Construction Contract 20-181 with Fleming Environmental, Inc. for Fuel Tank Infrastructure Phase II
Attachments: 1. Amendment #1 - Furnish Dispensers, 2. CON-RESD-PMD-082520-Amendment No. 1 to Contract No. 20-181 for Fuel Tank Infrastructure Phase II, 3. Item #54 Executed BAI, 4. 20-181-A-1 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

August 25, 2020

 

FROM

TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management

         

SUBJECT                      

Title                     

Amendment No. 1 to Construction Contract 20-181 with Fleming Environmental, Inc. for Fuel Tank Infrastructure Phase II

End

 

RECOMMENDATION(S)

Recommendation

Approve Amendment No. 1 to Contract No. 20-181 with Fleming Environmental, Inc. for the Fuel Tank Infrastructure Phase II Project in Baker, increasing the total contract amount by $9,755 from $627,894 to $637,649, and extending the completion date from September 8, 2020 to December 7, 2020 for the Fuel Tank Infrastructure Phase II Project located at 72734 Baker Blvd, in Baker (Four Votes Required).

(Presenter: Terry W. Thompson, Director, 387-5252)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Operate in a Fiscally-Responsible and Business-Like Manner.

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

 

FINANCIAL IMPACT

This item does not require additional Discretionary General Funding (Net County Cost).  The Fuel Tank Infrastructure Phase II Project (Project) budget of $1,000,000 is comprised of the following components: 

 

Construction Management

$      71,901

Design

$      79,756

Labor Compliance

$      32,060

Materials Testing/ Inspection

$      65,600

Project Management

$      60,000

Construction

$    627,894

Amendment No. 1

$        9,755

Construction Contingency

$      53,034

Total Project Budget

$ 1,000,000

 

The project budget of $1,000,000 is funded from the Fleet Management Department (Fleet) Internal Service Fund Net Position.  Sufficient appropriation and revenue is included in the 2020-21 Capital Improvement Program (CIP) budget. 

 

BACKGROUND INFORMATION

The Project is located at 72734 Baker Blvd. in Baker and will install two above ground 10,000-gallon fuel tanks, one with unleaded fuel and the other with diesel fuel adjacent to the Baker Fire Station #53 to serve County employees that work in and around the Baker area.

 

Amendment No. 1 will compensate Fleming Environmental, Inc., (Fleming) for the increased cost of procuring equipment differing from that identified in the original construction documents due to supply chain issues.  The additional costs/scope of work resulted from requests for the Contractor to provide equipment not identified in the bid documents because the originally identified equipment was unavailable. 

 

Amendment No. 1 will also extend the Contract Time with Fleming Environmental, Inc. from 120 calendar days to 210 calendar days, a 90 calendar day, no dollar amount time extension, to allow for procurement of equipment due to supply chain delays as a result of factory shut downs during the COVID-19 pandemic.  The Contract Time is the agreed upon period of time allotted to Contractor to achieve completion of the entire scope of work, without the imposition of liquidated damages.  Extensions of the Contract Time are permitted by section 3.1 of the Contract, subject to written approval of the County.  At all times the Contract as a whole remains in full force and effect until all issues relating to the Contract have been resolved. 

 

A summary of costs associated with the original contract, and Amendment No. 1 are as follows:

 

Date

Description

Amount

04-07-20

Original Contract

$627,894

08-25-20

Amendment No. 1:  Additional scope of work (1.6% over original contract)

$9,755

 

Total amount of revised contract

$637,649

 

PROCUREMENT

The unanticipated additional cost items in Amendment no. 1 are related to unforeseen supply chain related events that took place after the competitive bid processes that resulted in the original contract with Fleming Environmental, Inc. Therefore, no additional procurement activities are required.

 

Per Public Contract Code sections 20136 and 20137, Board of Supervisors approval is required for this amendment to the contract with Fleming Environmental, Inc.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5437) on July 8, 2020; Fleet Management (Ron Lindsey, Director, 387-7870) on July 10, 2020; Purchasing Department (Bruce Cole, Supervising Buyer, 387-2148) on July 10, 2020; Project Management Division (Don Day, Interim Deputy Director, 387-5000) on July 27, 2020; Real Estate Services (Jennifer Costa, Assistant Director, 387-5000) on July 28, 2020; Finance (Wen Mai, 387-4020, Principal Administrative Analyst), on August 4, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on August 7, 2020.

 

(BR: 771-1168)