Skip to main content
San Bernardino header
San Bernardino govDelivery
File #: 6513   
Type: Consent Status: Passed
File created: 7/29/2022 Department: County Administrative Office
On agenda: 8/9/2022 Final action: 8/9/2022
Subject: Budget Adjustment for the Chino Airport Groundwater Remedial Project
Attachments: 1. Item #18 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

August 9, 2022

 

FROM

LEONARD X. HERNANDEZ, Chief Executive Officer, County Administrative Office 

         

SUBJECT                      

Title                     

Budget Adjustment for the Chino Airport Groundwater Remedial Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve a budget adjustment to Capital Improvement Program Project No. 18-222, using $15 million from the Chino Plume Needs Reserve for the Chino Airport Groundwater Remedial Project (WBSE 10.10.0556).

2.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post budget adjustments, as detailed in the Financial Impact Section (Four votes required).

(Presenter: Matthew Erickson, County Chief Financial Officer, 387-5423)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Operate in a Fiscally-Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Board of Supervisors (Board) has currently allocated $46 million of Discretionary General Funding for expenses associated with the groundwater investigation and remedial project, known as the Chino Airport Groundwater Remedial Action Project (Remedial Project), including $21 million in a capital project budget and $25 million set aside in the Chino Plume Needs Reserve (Reserve). In addition, the Board also contributed $20 million of American Rescue Plan Act (ARPA) funds to partially fund the Remedial Project, resulting in a total allocation of $66 million for this project.

 

A recommended use of $15 million from the Reserve, which was approved by the Board on June 14, 2022 (Item No. 103), is needed sooner than anticipated for immediate costs for property acquisitions and consultant services.  These known costs were initially planned to be funded with ARPA funds; however, it has been determined that ARPA funds are more suited to pay for future fiscal year construction costs associated with the project.  As a result, it is recommended to use the Board-approved reserve for this year’s project costs instead of future year construction costs.  The overall current estimated cost of the project has not changed, but is expected to require additional funding in future years. The following budget adjustments are requested:

 

Fund Center

Commitment/GL Account

Description

Action

Amount

WBSE

1000

37008760

Chino Plume      Needs Reserve

Decrease

$15,000,000

 

1161161000

55305030

Operating Transfers Out

Increase

$15,000,000

 

7700003100

40909975

Operating Transfers In

Increase

$15,000,000

10.10.0556

7700003100

54104010

Improvements to Land

Increase

$15,000,000

10.10.0556

 

BACKGROUND INFORMATION

San Bernardino County (County), under order from the Santa Ana Regional Water Quality Control Board, is in the process of implementing an Interim Remedial Action Plan for groundwater contaminated with volatile organic compounds (VOCs) proximate to its County-operated Chino Airport. The preferred remedial alternative includes treatment and control measures to clean up the contaminated groundwater, including a pump, treat system, and institutional controls. The remedial plan will reduce toxicity, mobility, and volume in contaminated groundwater, and is most likely to prevent future impacts to downgradient and off-site groundwater resources. 

 

On June 14, 2022 (Item No. 103), as part of the County’s 2022-23 Budget, the Board approved the Chino Plume Needs General Fund Reserve in the amount of $25 million to fund future costs associated with the Remedial Project that were anticipated to begin in 2024-25. However, there is an immediate need to fund costs in the amount of $15 million, which are within the current total estimated project costs. This will provide the funding for costs related to property acquisitions for easements associated with five well sites, consulting services for technical assistance of the Remedial Project, and ongoing construction costs after ARPA funds have been expended.  Significant additional one-time expenses are still anticipated in future years.

 

Approval of this recommendation aligns with the County and the Chief Executive Officer’s goal and objective to operate in a fiscally-responsible and business-like manner and will allow the County to stay in compliance with the Clean-up and Abatement Orders issued by the Santa Ana Regional Water Quality Control Board.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Kristina M. Robb, Principal Assistant County Counsel, 387-5455) on July ---26, 2022; Auditor-Controller/Treasurer/Tax Collector (Vanessa Doyle, Deputy Chief Controller, 387-5669) on July ---7, 2022; Finance (Yael Verduzco, Principal Administrative Analyst, 387-5285, and Carl Lofton, Administrative Analyst, 387-5404) on June 27, 2022; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on June 27, 2022.