Skip to main content
File #: 13755   
Type: Consent Status: Passed
File created: 2/27/2026 Department: Project and Facilities Management
On agenda: 3/10/2026 Final action: 3/10/2026
Subject: Budget Adjustment and Construction Contract with Coelho, Inc., for the Arrowhead Regional Medical Center Central Plant Medical Vacuum System Replacement Project
Attachments: 1. CON-PFMD-031026-BA & Contract to Coelho for ARMC Central Plant Medical Vacuum System, 2. Item #24 Executed BAI, 3. 26-158 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

                                          March 10, 2026

 

FROM

MOE YOUSIF, Interim Director, Project and Facilities Management Department

ANDREW GOLDFRACH, ARMC Chief Executive Officer, Arrowhead Regional Medical Center

         

SUBJECT                      

Title                     

Budget Adjustment and Construction Contract with Coelho, Inc., for the Arrowhead Regional Medical Center Central Plant Medical Vacuum System Replacement Project

End

 

RECOMMENDATIONS

Recommendation

1.                     Approve a budget increase in the amount of $305,937 to Capital Improvement Program Project No. 23-016, increasing the total project budget from $1,876,698 to $2,182,635, for the Arrowhead Regional Medical Center Central Plant Medical Vacuum System Replacement Project in Colton.

2.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post necessary budget adjustments to the Capital Improvement Program and Arrowhead Regional Medical Center Central Plant Medical Vacuum System Replacement Project budget, as detailed in the Financial Impact section (Four votes required).

3.                     Award Construction Contract to Coelho, Inc., in the amount of $1,599,950, with a construction completion date of 270 days from the date of issuance of the Notice to Proceed, for the Arrowhead Regional Medical Center Central Plant Medical Vacuum System Replacement Project in Colton.

4.                     Authorize the Director of the Project and Facilities Management Department to order any necessary changes or additions in the work being performed under the contract, for a total not to exceed $92,497.50 pursuant to Public Contract Code Section 20142.

5.                     Authorize the Director of the Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.

(Presenter: Moe Yousif, Interim Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The recommended contract award of $1,599,950 will be funded through the Arrowhead Regional Medical Center (ARMC) Central Plant Medical Vacuum System Replacement (Project) (WBSE 10.10.1321), within the total project budget of $2,182,635. The budget increase of $305,937 will be funded by the available unrestricted net position.

 

Approval of this item will allow the Auditor-Controller/Treasurer/Tax Collector to post the following budget adjustments to the 2025-26 Capital Improvement Program and Arrowhead Regional Medical Center budget:

Funds Center

Commitment Item

Description

Action

Amount

WBSE

7700004204

54304030

Structures and Improvements to Structures

Increase

$305,937

10.10.1321

7700004204

40909975

Operating Transfers In

Increase

$305,937

10.10.1321

9186104200

55305030

Operating Transfers Out

Increase

$305,937

9110004200

40909995

Residual Equity Transfer In

Increase

$305,937

 

The revised Project budget of $2,182,635 is comprised of the following components:

 

Description

Amount

Project Design

$252,301   

Project Management, Inspection and Testing

$235,387

Construction

$1,599,950

Construction Contingency

$79,997   

Project Contingency

$15,000   

Total Project Budget

$2,182,635

 

BACKGROUND INFORMATION

The recommended action will award a construction contract to Coelho, Inc. for the Project located in Colton, which will remove and replace the existing central plant medical vacuum system. The new vacuum system will enhance reliability, redundancy and code compliance at the ARMC facility, ensuring uninterrupted clinical operations, improved patient safety and long-term infrastructure resiliency to support current and future healthcare demands.

 

On November 9, 2025, pursuant to County Policy 11-15, the Assistant Executive Officer (AEO) determined that the Project, involving the replacement and upgrade of the existing central plant medical vacuum system with no expansion of use, is categorically exempt from the California Environmental Quality Act (CEQA) under CEQA Guidelines Section 15301(a) for existing facilities. No further environmental review is required.

 

This increase of $305,937 is to capture the full costs of the project including bid pricing reflective of prevailing construction costs, material escalation costs, construction contingency and project administration, inspector of record and labor compliance costs.

This project is consistent with the Board of Supervisors approved CIP Project No. 23-016.

 

PROCUREMENT

On November 9, 2025, the AEO, pursuant to County Policy 11-15, authorized the Project and Facilities Management Department (PFMD) to advertise the project for competitive bids via Request for Proposals (RFP) No. ANE223-ANE2C-6171. PFMD advertised for bids on the County Electronic Procurement Network (ePro) on November 12, 2025. On November 21, 2025, at 8:00 am, contractors attended a mandatory job walk.

 

On January 6, 2026, the following three bids were received:

 

Name

Location

Bid

Coelho, Inc.

Santee, CA

$1,599,950

Healthcare Design and Construction, LLC

Tustin, CA

$1,854,105

HPS Mechanical

Bakersfield, CA

$1,902,543

 

PFMD recommends the Board award the construction contract to Coelho, Inc., the lowest responsive and responsible bidder.  No protest or appeals were received on behalf of the Project.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Daniel Pasek, Deputy County Counsel, 387-5455) January 27, 2026; Arrowhead Regional Medical Center (Andrew Goldfrach, ARMC Chief Executive Officer, 580-6170) on January 27, 2026; Purchasing (Ariel Gill, Supervising Buyer, 387-2070) on January 27, 2026; Auditor-Controller/Treasurer/Tax Collector (Charlene Huang, Auditor-Controller Manager, 382-7022) on January 30, 2026; Project and Facilities Management (Rob Gilliam, Chief of Project Management, 387-5115) on February 2, 2026; and County Finance and Administration (Jenny Yang, Administrative Analyst, 387-4884, and Yael Verduzco, Principal Administrative Analyst, 387-5285) on February 23, 2026.

 

(GL: 387-5000)