San Bernardino header
File #: 10720   
Type: Consent Status: Passed
File created: 8/12/2024 Department: Project and Facilities Management
On agenda: 8/20/2024 Final action: 8/20/2024
Subject: Amendment and Change Order No. 2 to Construction Contract with Icon West, Inc. for the Acquisition and Improvements Project in Colton
Attachments: 1. ADD-CON-PFMD-082024-Amendment No.2 to Construction Contract with Icon West, 2. ADD-CON-PFMD-082024-Change Order No.2 to Contract with Icon West, 3. Item #55 Executed BAI, 4. 22-1071 C-2 Executed Contract, 5. 22-1071 A-2 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

August 20, 2024

 

FROM

DON DAY, Director, Project and Facilities Management Department

LYNN FYHRLUND, Chief Information Officer, Innovation and Technology Department

         

SUBJECT                      

Title                     

Amendment and Change Order No. 2 to Construction Contract with Icon West, Inc. for the Acquisition and Improvements Project in Colton

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve Amendment No. 2 to Contract No. 22-1071 with Icon West, Inc., increasing the contract amount by $248,231, from $24,780,075 to $25,028,306, for the Acquisition and Improvements Project, for the Innovation and Technology Department in Colton (Four votes required).

2.                     Approve Change Order No. 2 to Contract No. 22-1071 with Icon West, Inc., increasing the contract amount by $705,073, from $25,028,306 to $25,733,379, for the Acquisition and Improvements Project, for the Innovation and Technology Department in Colton (Four votes required).

(Presenter: Don Day, Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Operate in a Fiscally-Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Fund (Net County Cost). The Acquisition and Improvements Project (Project) (WBSE 10.10.0768) budget of $54,240,792 is comprised of the following components:

 

Description

Amount

Project Acquisition

$14,500,000

Project Management and Inspection

$  1,500,000

Design

$  2,300,000

Construction

$23,766,681

Construction Contingency

$     409,970

Labor Compliance

$       57,443

Materials Testing/ Inspection

$     120,000

Software/ Hardware

$  3,500,000

Furniture, Fixtures and Equipment

$  6,120,000

Amendment No. 1

$     710,903

Change Order No. 1

$     302,491

Amendment No. 2

$     248,231

Change Order No. 2

$     705,073

Total Project Budget

$54,240,792

 

Sufficient appropriation and revenue are included in the 2024-25 Capital Improvement Program (CIP) budget.

 

BACKGROUND INFORMATION

The Project, established in 2018 on behalf of the Innovation and Technology Department (ITD), is a design-bid-build construction project. The ongoing construction to renovate the 75,000 square foot three-story building located in Colton will house ITD’s staff and consists of removing existing interior office walls for an open floor plan for cubicles, installation of new office furniture, installation of new site security fencing and solar canopies, as well as installation of two 750-kilowatt generators to provide emergency backup power for the facility.

 

Approval of Amendment No. 2 will compensate Icon West, Inc. (IWI), in the amount of $248,231, for the additional work needed due to unexpected site conditions, including additional design work needed to provide access to Colton Electric’s existing transformer, unforeseen conditions related to improper structural framing found after demolition of various areas throughout the building, and modifications to the vehicle gate per City of Colton requirements.

 

Approval of Change Order No. 2 will compensate IWI, in the amount of $705,073, for additional work required to incorporate modifications related to revisions to the contract drawings not specified in the original bid documents, County-directed changes made in the field, or responses to IWI requests for information.

 

On May 24, 2022 (Item No. 68) the Board of Supervisors (Board) authorized the Project and Facilities Management Department (PFMD) to advertise for competitive bids via Request for Proposals ANE221-ANE2C-4606 for the Project.

 

On October 25, 2022 (Item No. 53), the Board awarded a construction contract to IWI, the lowest responsive and responsible bidder, the amount of $23,766,681.

 

On December 5, 2023 (Item No. 43), the Board approved Amendment No. 1 in the amount of $710,903 and Change Order No. 1 in the amount of $302,491 to the construction contract with IWI, increasing the contract to a total of $24,780,075.

 

The unanticipated additional costs related to Amendment No. 2 and Change Order No. 2 are related to events that took place after the competitive bid process that resulted in the original contract award to IWI. Therefore, no additional procurement activities are required.

 

Public Contract Code section 20136 requires all change orders and amendments to construction contracts must be approved by a two-thirds votes’ approval of the Board.

 

PROCUREMENT

Not Applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Julie Surber, Principal Assistant County Counsel, 387-5455) on June 24, 2024; Innovation and Technology (Lynn Fyhrlund, Chief Information Officer, 388-5501) on July 8, 2024; Purchasing (Leo Gomez, Supervising Buyer, 387-2148) on July 10, 2024; Project and Facilities Management (Robert Gilliam, Chief of Project Management, 387-5000) on July 11, 2024; Finance (Garrett Baker, Administrative Analyst, 387-3077) on August 2, 2024; and County Finance and Administration (Valerie Clay, Deputy Executive Officer, 387-5423) on August 5, 2024.