Skip to main content
File #: 13152   
Type: Consent Status: Agenda Ready
File created: 11/5/2025 Department: Project and Facilities Management
On agenda: 11/18/2025 Final action:
Subject: Budget Adjustment and Construction Contract with ACCO Engineered Systems, Inc., for the Arrowhead Regional Medical Center Cooling Tower Replacement Project
Attachments: 1. ATT-PFMD-111825-Bid Tabulation ARMC Cooling Tower Replacement, 2. ATT-PFMD-111825-ACCO Engineering Bid- ARMC Cooling Tower Replacement, 3. ATT-PFMD-111825-Addendum 1 ARMC Cooling Tower Replacement, 4. ATT-PFMD-111825-Addendum 2 ARMC Cooling Tower Replacement, 5. R1-CON-PFMD-111825-Construction Contract ARMC Cooling Tower Replacement
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

November 18, 2025

 

FROM

DON DAY, Director, Project and Facilities Management Department

ANDREW GOLDFRACH, ARMC Chief Executive Officer, Arrowhead Regional Medical Center

    

SUBJECT                      

Title                     

Budget Adjustment and Construction Contract with ACCO Engineered Systems, Inc., for the Arrowhead Regional Medical Center Cooling Tower Replacement Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve the following addenda to the bid documents for the Arrowhead Regional Medical Center Cooling Tower Replacement Project:

a.                     Addendum No. 1, dated July 31, 2025, to the bid documents, which revised the bid opening date.

b.                     Addendum No. 2, dated August 5, 2025, to the bid documents, which provided answers to pre-bid questions, and modified plans and specification documents.

2.                     Award Construction Contract, in the amount of $10,641,888, to ACCO Engineered Systems, Inc., for a contract period of 450 calendar days from the date of the issuance of the Notice to Proceed, for the Arrowhead Regional Medical Center Cooling Tower Replacement Project in Colton.

3.                     Authorize the Director of the Project and Facilities Management Department to order any necessary changes or additions in the work being performed under the contract, for a total not to exceed $210,000, pursuant to Public Contract Code Section 20142.

4.                     Authorize the Director of Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.

5.                     Approve a budget increase in the amount of $2,272,425 to Capital Improvement Program Project No. 21-047, increasing the total project budget from $11,256,150 to $13,528,575, for the Arrowhead Regional Medical Center Cooling Tower Replacement Project.

6.                     Authorize the Auditor-Controller/Treasure/Tax Collector to post necessary budget adjustments, as detailed in the Financial Impact section (Four votes required).

(Presenter: Don Day, Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve ARMC County Hospital Operations.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The budget adjustment of $2,272,425 will increase the Arrowhead Regional Medical Center (ARMC) Cooling Tower Replacement Project (Project) (WBSE 10.10.1054) budget from $11,256,150 to $13,528,575. The adjustment will be funded by additional revenue associated with the California Quality Incentive Program. Approval of this item will allow the Auditor-Controller/Treasurer/Tax Collector to post the following revenue adjustments to the 2025-26 Capital Improvement Program (CIP) Project No. 21-047 budget:

 

Funds Center

Commitment Item

Description

Action

Amount

WBSE

9110004200

40449625

ARMC - Managed Care Internal Governmental Transfer

Increase

$2,272,425

-

9186104200

55305030

Operating Transfers Out

Increase

$2,272,425

-

7700004204

54304030

Structures and Improvements to Structures

Increase

$2,272,425

10.10.1054

7700004204

40909975

Operating Transfers In

Increase

$2,272,425

10.10.1054

 

The revised Project budget of $13,528,575 is comprised of the following components:

 

Description

Amount

Project Contingency

$212,457 

Project Design

$660,241 

Construction Contingency

$1,064,189 

Project Management, Inspection and Testing

$949,800

Construction

$10,641,888

Total Project Budget

$13,528,575

 

BACKGROUND INFORMATION

Approval of this item will award a construction contract to ACCO Engineered Systems Inc., for the Project located in Colton. The Project will remove and replace the existing cooling tower, structural steel, and roof system, all of which have reached the end of their useful life. The replacement equipment and infrastructure will ensure continued utility service capacity, which is critical to hospital operations.

 

The budget increase will allow ARMC to revise the project scope to include unforeseen work identified during the bidding process, including extensive equipment deterioration and corrosion. The supporting structural beams were deteriorated to the point that replacement was advised in lieu of patching for the longevity of the equipment and to further support hospital operations. The cost of repairing would be prohibitive and costly, negating any benefit versus replacement.

 

On September 26, 2023 (Item No. 42), the Board of Supervisors (Board) determined the Project to be categorically exempt under Section 15302, Class 2, subsections (b) and (c) of the California Environmental Quality Act (CEQA) Guidelines (Title 14, California Code of Regulations). No further environmental review is required at this time. The Board also authorized the Director of the Project and Facilities Management Department (PFMD) to advertise for competitive bids for the Project.

 

On September 29, 2023, PFMD initially advertised the Project; however, the solicitation was cancelled on November 29, 2023, prior to the receipt of any bids, to allow comprehensive revisions to the scope and design in response to Request for Information (RFI) feedback. The Project was sent back to the design stage in order to incorporate all the necessary structural changes and extensive California Department of Health Care Access and Information approval. The Project was subsequently re-advertised on July 3, 2025, with additional clarifying drawings through Amended Construction Document 0001 (ACD 0001), pursuant to County Policy 11-15.

 

On March 11, 2025 (Item No. 31), the Board approved a budget increase of $5,924,660, increasing the total project budget from $5,331,490 to $11,256,150, to support the incorporation of ACD 0001 and provide sufficient appropriation authority for the revised scope, which changed from refurbishing to fully replacing the cooling towers and roof due to severe corrosion and structural deterioration and added temporary cooling towers to maintain hospital operations during construction.

 

A further budget increase is now recommended to accommodate additional unforeseen work due to structural issues identified in ACD 0001, including extensive equipment deterioration and corrosion not previously captured in the initial scope. To address these conditions, additional equipment and structural modifications were incorporated through Amended Construction Document 0002 (ACD 0002).

 

This Project is consistent with the County Administrative Office-approved CIP Project No. 21-047.

 

PROCUREMENT

On September 26, 2023 (Item No. 42), the Board authorized PFMD to advertise for competitive bids. PFMD first advertised on September 29, 2023; the solicitation was cancelled on November 29, 2023 to incorporate RFI-driven scope and design revisions.

 

The Project was re-advertised on July 3, 2025, via Daily Press and County Electronic Procurement Network (ePro) via Competitive Bid No. ANE223-ANE2C-5946. The following addenda were issued:

 

1.                     Addendum No. 1, dated July 31, 2025, revised the bid opening date to August 13, 2025.

2.                     Addendum No. 2, dated August 5, 2025, provided responses to bidder inquiries and issued ACD 0002 which modified plans and specifications for the Project.

 

On August 13, 2025, the following two bids were received:

 

Name

Location

Bid

ACCO Engineered Systems, Inc.

Pasadena, CA

$10,641,888

Mesa Energy Systems, Inc.

Irvine, CA

$11,489,522

 

PFMD recommends the Board award the construction contract to ACCO Engineered Systems Inc., the lowest responsive and responsible bidder.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Daniel Pasek, Deputy County Counsel, 387-5455) September 10, 2025; Arrowhead Regional Medical Center (Andrew Goldfrach, ARMC Chief Executive Officer, 580-6170) on September 10, 2025; Purchasing (Ariel Gill, Supervising Buyer, 387-2070) on September 10, 2025; Auditor-Controller/Treasurer/Tax Collector (Charlene Huang, Auditor-Controller Manager, 382-7022) on September 16, 2025; Project and Facilities Management (Robert Gilliam, Chief of Project Management, 387-5000) on September 17, 2025; and County Finance and Administration (Jenny Yang, Administrative Analyst, 387-4884, and Yael Verduzco, Principal Administrative Analyst, 387-5285) on November 2, 2025.

 

(GL: 387-5000)