Skip to main content
File #: 9808   
Type: Consent Status: Passed
File created: 3/28/2024 Department: Public Works-Transportation
On agenda: 4/9/2024 Final action: 4/9/2024
Subject: Utility Agreement with East Valley Water District for Waterline Relocations for the Little Third Street and Little Tippecanoe Avenue Project in the San Bernardino Area
Attachments: 1. MAP-PW-Trans 4-9-24 Utility Agr with EVWD for Waterline Relocations for Little Third Street and Little Tippecanoe Avenue Project, 2. ADD-AGR-PW-Trans 4-9-2024 Utility Agr with EVWD for Waterline Relocations for Little Third Street and Little Tippecanoe Avenue Project, 3. Item #46 Executed BAI, 4. 24-311 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

April 9, 2024

 

FROM

NOEL CASTILLO, Director, Department of Public Works - Transportation

 

SUBJECT

Title

Utility Agreement with East Valley Water District for Waterline Relocations for the Little Third Street and Little Tippecanoe Avenue Project in the San Bernardino Area

End

 

RECOMMENDATION(S)

Recommendation

Approve Utility Agreement with the East Valley Water District for the relocation of East Valley Water District’s waterline facilities that conflict with the San Bernardino County’s Little Third Street and Little Tippecanoe Avenue Project in the San Bernardino area, at an estimated cost not to exceed amount of $464,888, for a contract term commencing April 9, 2024, and that shall terminate upon receipt of a Notice of Completion of the Project, or April 9, 2027, whichever occurs first.

(Presenter: Noel Castillo, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Little Third Street and Little Tippecanoe Avenue in the San Bernardino Area (Project) is funded with Gas Tax, Measure I Local Streets Program San Bernardino Valley Subarea, and anticipated Federal Congressionally Directed Spending revenue. The Project’s waterline relocations will be funded with Measure I Local Streets Program San Bernardino Valley Subarea funds. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2023-24 Road Operations budget (66500002000 34H15122/TX1825) and will be included in future recommended budgets.

 

BACKGROUND INFORMATION

The Project involves pavement rehabilitation, new asphalt concrete pavement, sidewalks, curb and gutter, storm drains, fencing, streetlights, and new curb ramps in accordance with current design standards and pursuant to the Americans with Disabilities Act (ADA) guidelines. 

 

On July 11, 2023 (Item No. 34), the Board of Supervisors (Board) approved and determined the Project was exempt under the California Environmental Quality Act (CEQA) and a Notice of Exemption was filed. No further action related to CEQA is required at this time.

 

On November 14, 2023 (Item No. 69), the Board authorized the acquisition of 18 temporary construction easements (TCEs) from 16 property owners, over portions of certain real properties. Although there are 18 TCEs, there are only 17 Acquisition Agreements, as two properties are included in one agreement among the 16 property owners.

 

Subsequent to the Board’s approval of the Project and the County’s acquisition of the easements, Department staff determined during the design phase that the Project would impact East Valley Water District’s (District) existing waterlines, water meters, fire hydrants, and appurtenant structures, necessitating a relocation in order to accommodate the Project within the right-of-way. The Utility Agreement (Agreement) with the District will provide for the relocation of the District’s waterlines, water meters, fire hydrants, and appurtenant structures, with the District to be the lead agency for the design and the relocation work.  Given that the District possesses prior rights within the public right-of-way on Little Third Street, from Palm Lane east to Pedley Road, the County will pay for the design and relocation costs, at an estimated amount not to exceed $464,888.

 

The County has requested that the District complete the above relocation and installation work prior to the commencement of the Project. The proposed Agreement sets forth the terms and conditions under which the District will relocate and install District’s facilities, subject to reimbursement from County, for a contract term commencing April 9,2024, that shall terminate upon receipt of a Notice of Completion of the Project, or April 9, 2027, whichever occurs first. The Agreement may be terminated by either party, with or without cause, upon 30 days advance written notice. Upon completion of the relocation of the District facilities under the Agreement, the District shall own, operate, and maintain its facilities.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on February 14, 2024; Finance (Jessica Trillo, Administrative Analyst, 387-4222) on March 18, 2024; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on March 24, 2024.