Skip to main content
File #: 11594   
Type: Consent Status: Passed
File created: 1/17/2025 Department: Auditor-Controller/Treasurer/Tax Collector
On agenda: 1/28/2025 Final action: 1/28/2025
Subject: Employment Contract for Auditor-Controller/Treasurer/Tax Collector Property Tax Collection System Implementation Officer
Attachments: 1. CON-ATC-1-28-25-Linda Mikulski, 2. Item #17 Executed BAI, 3. 25-57 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

January 28, 2025

FROM
ENSEN MASON, Auditor-Controller/Treasurer/Tax Collector

SUBJECT
Title
Employment Contract for Auditor-Controller/Treasurer/Tax Collector Property Tax Collection System Implementation Officer
End

RECOMMENDATION(S)
Recommendation
Approve Employment Contract with Linda Mikulski, as an Auditor-Controller/Treasurer/Tax Collector Property Tax Collection System Implementation Officer, to provide service and support to the Auditor-Controller/Treasurer/Tax Collector on the Property Tax Legacy Systems Replacement Project, for the period of February 8, 2025, through October 3, 2025, for the estimated cost of $176,693 (Salary - $119,325, Benefits - $57,368).
(Presenter: Ensen Mason, Auditor-Controller/Treasurer/Tax Collector, 382-7000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The position will be funded with a budget transfer between the Automated Systems Development Fund (1165901042) and the Auditor-Controller/Treasurer/Tax Collector's General Fund (3407001000). Sufficient appropriation and revenue have been included in the Automated Systems Development Fund and the Auditor-Controller/Treasurer/Tax Collector's (ATC) 2024-25 budgets and will be included in the 2025-26 Recommended Budget.

BACKGROUND INFORMATION
The Property Tax Legacy Systems Replacement Project (Project) was initiated in 2019. On May 24, 2022 (Item No. 25), the Board of Supervisors approved a 10-year, $58 million contract to implement and support the solution scheduled to go live in July 2025. The enterprise solution takes Assessor-Recorder-County Clerk property assessments and then technologically enables ATC's business...