REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
May 18, 2021
FROM
BRENDON BIGGS, Director, Department of Public Works - Solid Waste Management
SUBJECT
Title
Contract with SCS Field Services for the Construction of the Landfill Gas Collection and Control System and Treatment Facility at the Landers Sanitary Landfill
End
RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1 to the bid documents, issued on March 2, 2021, for the construction of the Landfill Gas Collection and Control System and Treatment Facility at the Landers Sanitary Landfill.
2. Approve Addendum No. 2 to the bid documents, issued on March 10, 2021, for the construction of the Landfill Gas Collection and Control System and Treatment Facility at the Landers Sanitary Landfill.
3. Award a construction contract to SCS Field Services, (Long Beach, CA) in the amount of $2,355,863.30 for the construction of the Landfill Gas Collection and Control System and Treatment Facility at the Landers Sanitary Landfill.
4. Authorize a contingency fund of $235,586 for the Landfill Gas Collection and Control System Treatment Facility at the Landers Sanitary Landfill.
5. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not-to-exceed $130,293.17 pursuant to Public Contract Code Section 20142.
6. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost) as the Department of Public Works - Solid Waste Management Division (SWMD) is financed by fee revenue....