Subject: Plans and Specifications for Southwest Del Rosa Area Americans with Disabilities Act Ramps Project
Attachments: 1. ATT-PW-Trans 4-25-23 Plans and Specs for SW Del Rosa Area ADA Ramps Project - Specs, 2. MAP-PW-Trans 4-25-23 Plans and Specs for SW Del Rosa Area ADA Ramps Project, 3. ATT-PW-Trans 4-25-23 Plans and Specs for SW Del Rosa Area ADA Ramps Project - Plans, 4. Item #51 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

April 25, 2023

 

FROM

BRENDON BIGGS, Director, Department of Public Works - Transportation

 

SUBJECT

Title

Plans and Specifications for Southwest Del Rosa Area Americans with Disabilities Act Ramps Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve the plans and specifications for the Southwest Del Rosa Area Americans with Disabilities Act Ramps Project, as signed and sealed by a registered civil engineer.

2.                     Authorize the Director of the Department of Public Works to advertise the Southwest Del Rosa Area Americans with Disabilities Act Ramps Project for formal bids.

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Southwest Del Rosa Area Americans with Disabilities Act (ADA) Ramps Project (Project) is funded with Discretionary General Funding allocated for the Department of Public Works (Department) annual Maintenance of Effort requirement and Senate Bill 1 (SB1) Road Maintenance and Rehabilitation Account (RMRA) revenue.  The requested actions are administrative in nature with minimal financial impact of approximately $1,000. Sufficient appropriation and revenue are included in the Department’s 2022-23 Road Operations budget (6650002000 20H15033).

 

BACKGROUND INFORMATION

The Project involves constructing new and replacing existing curb ramps at 39 locations in the Del Rosa area in accordance with current design standards and pursuant to the ADA guidelines.  Other improvements include reconstruction of sidewalks, driveways, spandrels, cross gutters, and minor street improvements, as needed.  Certain areas will also require root pruning and the installation of a 24” root barrier to protect sidewalks from future damage.  All work for the Project will be done within the existing right-of-way.

 

This Project was prioritized by the Board of Supervisors (Board) as part of the 2020-21 SB1 RMRA project list, which was approved on April 21, 2020 (Item No. 45).  Updates to existing ADA compliant curb ramps or installation of new ADA compliant curb ramps for the Project are required under the federal “2013 Department of Justice/Department of Transportation Joint Technical Assistance on the Title II of the AD A Requirements to Provide Curb Ramps when Streets, Roads, or Highways are Altered through Resurfacing” guidelines. 

 

On September 13, 2022 (Item No. 51), the Board determined the Project was exempt under the California Environmental Quality Act, approved the Project as defined in the Notice of Exemption, and directed the Clerk of the Board to file and post said notice.

 

This Project aligns with the County and the Chief Executive Officer’s goals and objectives of ensuring development of a well-planned, balanced, and sustainable County and providing for the safety of County residents by improving access for all pedestrians, including those with disabilities.

 

The Project includes an allowance in the amount of $25,000 for differing site conditions associated with unforeseen differing site conditions and utility conflicts.

 

PROCUREMENT

The Project will be advertised to invite formal bids in accordance with Section 22037 of the California Public Contract Code.  The Department anticipates returning to the Board for an award of the construction contract in Summer 2023.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on March 30, 2023; Finance (Carl Lofton, Administrative Analyst, 387-5404) on April 10, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on April 10, 2023.