Subject: Board of Supervisors Discretionary Fund - District Specific Priorities Program - Lilac Avenue Streetlight Project
Attachments: 1. CON-MULTI-042523 CSA 70 SL-1 Lilac Avenue Streetlight Discretionary Funds, 2. Item #70 Executed BAI, 3. 23-317 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

SITTING AS THE GOVERNING BOARD FOR THE FOLLOWING:

SAN BERNARDINO COUNTY

 BOARD GOVERNED COUNTY SERVICE AREAS

AND RECORD OF ACTION

 

April 25, 2023

 

FROM

LEONARD X. HERNANDEZ, Chief Executive Officer, County Administrative Office

 

SUBJECT

Title

Board of Supervisors Discretionary Fund - District Specific Priorities Program - Lilac Avenue Streetlight Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Acting as the governing body of San Bernardino County:

a.                     Approve an allocation of $167,000 from the 2022-23 Fifth District’s Board of Supervisors Discretionary Fund - District Specific Priorities Program budget to County Service Area 70 SL-1.  

b.                     Approve contract with County Service Area 70 SL-1 to provide funding for the Lilac Avenue Streetlight Project in the amount of $167,000 for the contract term of April 25, 2023 through December 31, 2025.

c.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post the necessary budget adjustments, as detailed in the Financial Impact Section, to provide funding for the Lilac Avenue Streetlight Project (Four votes required).

2.                     Acting as the governing body of County Service Area 70 SL-1 Countywide:

a.                     Approve the Capital Improvement Program - County Service Area 70 SL-1 Countywide - Lilac Avenue Streetlight Project in the amount of $367,000.

b.                     Approve contract with San Bernardino County to receive funding for the Lilac Avenue Streetlight Project in the amount of $167,000 for the contract term of April 25, 2023 through December 31, 2025.

c.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post a budget increase of $367,000, as detailed in the Financial Impact Section, for the Lilac Avenue Streetlight Project (Four votes required).

 

(Presenter: Leonard X. Hernandez, Chief Executive Officer, 387-4811)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost).

 

On September 21, 2021 (Item No. 18) and November 16, 2021 (Item No. 33), the Board of Supervisors (Board) approved an allocation of $4 million and $7 million, respectively, to the Board Discretionary Fund - District Specific Priorities Program (Priorities Program) for each of the five supervisorial districts for projects that meet a public purpose and provide services to citizens that promote health, safety, economic well-being, and other public services that enhance quality of life and meet the needs of the County residents. On an annual basis, unspent appropriation for discretionary funding is carried over into the subsequent year’s budget.

 

The estimated cost of the Lilac Avenue Streetlight Project (Project) is $367,000. This item allocates $167,000 from the Fifth District’s Priorities Program budget for the Project.  The remaining $200,000 will be funded by available reserves of County Service Area (CSA) 70 SL-1 Countywide.

 

The following 2022-23 budget adjustments are needed to proceed with the Project:

 

 Fund Center

Commitment Item

 Description

Action

Amount

 San Bernardino County:

1025001000

53003305

Contributions to Other Agencies

Decrease

     $167,000

1025001000

55305030

Operating Transfers Out

Increase

     $167,000

 CSA 70 SL-1:

5750001300

54304030

Structures and Improvements

Increase

     $367,000

5750001300

40909975

Operating Transfers-In

Increase

     $167,000

5750001300

37008880

Available Reserves

Decrease

     $200,000

 

Sufficient appropriation for the Project will be included in future recommended budgets for CSA 70 SL-1 as needed.

 

BACKGROUND INFORMATION

CSA 70 SL-1, which was established by the Board on December 27, 1965, is managed and administered by the Department of Public Works - Special Districts (Department). CSA 70 SL-1 annually receives property taxes to fund the operation of approximately 3,511 streetlights in various unincorporated communities throughout the County. 

 

The Project consists of the installation of six pole-mounted streetlight heads on new, taller wooden poles along the west side of Lilac Avenue, between Easton Street and Walnut Avenue, in the Rialto area. This item is seeking Board approval of the Project and a contract between San Bernardino County and CSA 70 SL-1 in the amount of $167,000 to help fund the Project’s $367,000 estimated cost.

 

The Department anticipates returning to the Board at a later date for any necessary environmental or California Environmental Quality Act findings, approval of the Project’s plans and specifications, and authorization to advertise for bids.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by Auditor-Controller/Treasurer/Tax Collector (Charlene Huang, General Accounting Manager, 382-7022) on April 5, 2023; County Counsel (Julie Surber, Principal Assistant County Counsel, and Aaron Gest, Deputy County Counsel, 387-5455) on April 3, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635, and Stephanie Maldonado, Administrative Analyst, 387-4378) on April 5, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on April 10, 2023.