REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
December 5, 2023
FROM
DON DAY, Director, Project and Facilities Management Department
SUBJECT
Title
Amendment and Change Order to Construction Contract with Icon West, Inc. for the Acquisition and Improvements Project in Colton
End
RECOMMENDATION(S)
Recommendation
1. Approve Amendment No. 1 to Contract No. 22-1071 with Icon West Inc., in the amount of $710,903, increasing the contract from $23,766,681 to $24,477,584 and extending the construction completion date from May 31, 2024, to August 29, 2024, for the Acquisition and Improvements Project for the Innovation and Technology Department in Colton (Four votes required).
2. Approve Change Order No. 1 to Contract No. 22-1071 with Icon West, Inc., in the amount $302,491, increasing the contract from $24,477,584 to a total $24,780,075 for the Acquisition and Improvements Project for the Innovation and Technology Department in Colton (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Acquisition and Improvements Project (Project) (WBSE 10.10.0768) budget of $54,240,792 is comprised of the following components:
Description
Amount
Project Acquisition
$14,500,000
Project Management and Inspection
$ 1,500,000
Design
$ 2,300,000
Construction
$23,766,681
Construction Contingency
$ 1,363,274
Labor Compliance
$ 57,443
Materials Testing/ Inspection
$ 120,000
Software/ Hardware
$ 3,500,000
Furniture, Fixtures and Equipment
$ 6,120,000
Amendment No. 1
$ 710,903
Change Order No. 1
$ 302,491
Total Project Budget
$54,240,792