REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
April 7, 2026
FROM
BEAHTA R. DAVIS, Director, Regional Parks Department
SUBJECT
Title
Amendment to Agreement with KTU&A Planning and Landscape Architecture for a Master Plan Update for Prado Regional Park
End
RECOMMENDATION(S)
Recommendation
Approve Amendment No. 2 to Agreement No. 24-234 with KTU&A Planning and Landscaping Architecture, effective June 3, 2025, for a Master Plan Update for Prado Regional Park increasing the amount by $28,970, from $100,000 to $128,970, and extending the term from June 2, 2025 through June 30, 2026, for a total term of March 13, 2024 to June 30, 2026.
(Presenter: Beahta R. Davis, Director, 387-2340)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of Amendment No. 2 (Amendment) to Agreement No. 24-234 (Agreement) will not result in the use of Discretionary General Funding (Net County Cost). The Amendment to the Agreement with KTU&A Planning and Landscaping Architecture (KTU&A), in the amount of $28,970, will be funded from the Regional Parks Maintenance and Development Fund. Adequate appropriation and revenue are included in the Regional Parks Department 2025-26 budget.
BACKGROUND INFORMATION
On March 12, 2024 (Item No. 42), the Board of Supervisors (Board) approved the Agreement with KTU&A for the Master Plan Update for Prado Regional Park (Master Plan Update) with a term of March 13, 2024, through November 12, 2024.
On May 20, 2025 (Item No. 82), the Board approved Amendment No. 1 with KTU&A to extend the contract to June 2, 2025, to complete the Master Plan Update for Prado Regional Park. The Regional Parks Department (Department) became aware of the need to extend the Agreement after it had already expired on November 12, 2024, a...