File #: 10698   
Type: Consent Status: Passed
File created: 8/12/2024 Department: Public Works-Transportation
On agenda: 8/20/2024 Final action: 8/20/2024
Subject: Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List and Expenditures Strategy
Attachments: 1. ATT-PW-Trans-8-20-24 Measure I Local Street Pass-Thru 5 Year CIP Project List and ExpendituresAttach A Roads List, 2. ATT-PW-Trans-8-20-24 Measure I Local Street Pass-Thru 5 Year CIP Project List and ExpendituresCIP_Report_Template Attach A, 3. ATT-PW-Trans-8-20-24 Measure I Local Street Pass-Thru 5 Year CIP Project List and Expenditures Attach B, 4. ADD-RES-PW-Trans-8-20-ATT-PW-Trans-8-20-24 Measure I Local Street Pass-Thru 5 Year CIP Project List and Expenditures, 5. Item #67 Executed BAI, 6. 2024-130 Executed Resolution
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 20, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List and Expenditures Strategy
End

RECOMMENDATION(S)
Recommendation
Adopt Resolution approving the Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List and the Expenditure Strategy for 2024-25 through 2028-29.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost) or cost to the Department of Public Works (Department). The Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan (Plan) Project List (Project List) identifies projects assigned to utilize current and future Measure "I" sales tax revenues. Sufficient appropriation and revenue for continuing projects are included in the Department's 2024-25 Transportation Budget and will be included in future recommended budgets. Adjustments to the 2024-25 budget for new projects are not requested at this time but will be included in a future budget report, which will be presented to the Board of Supervisors (Board) for approval as necessary.

BACKGROUND INFORMATION
Adoption of the Resolution approves the Plan Project List from 2024-25 to 2028-29 (Attachment A) and the Expenditure Strategy (Attachment B). The Plan allocates funding to six subareas of the County: the Colorado River, Morongo Basin, North Desert, Mountains, San Bernardino Valley, and Victor Valley. These fu...