REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
March 24, 2020
FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management
SUBJECT
Title v
Award Construction Contract to Roadway Engineering & Contracting, Inc. for the Rancho Cucamonga - Modular Project
End
RECOMMENDATION(S)
Recommendation
1. Approve the following addenda to the Bid Documents for the Rancho Cucamonga - Modular Project.
a. Addendum No. 1 to the bid documents, issued January 10, 2020, which revised the bid closing date from February 5, 2020 at 1:00 p.m. to February 13, 2020 at 1:00 p.m., modified the bid documents, and added project drawings and specifications.
b. Addendum No. 2 to the bid documents, issued February 6, 2020, which provided project narrative, questions and answers.
2. Find the bid proposal from Michel Feghali (dba) SPAREA to be nonresponsive for failing to include a base bid amount in its bid proposal as required by the Bid Proposal.
3. Award a construction contract in the amount of $258,400 to Roadway Engineering & Contracting, Inc. of Fontana, CA for the Rancho Cucamonga - Modular Project (No. 10.10.0492), located at 9324 San Bernardino Rd., Rancho Cucamonga, CA 91730.
4. Authorize the Director of the Real Estate Services Department to order any necessary changes or additions in the work being performed under the contract for a total not to exceed $25,840, pursuant to Public Contract Code Section 20142.
5. Authorize the Director of the Real Estate Services Department to accept work when 100% complete, execute, and file the Notice of Completion.
(Presenter: Terry W. Thompson, Director, 387-5252)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Rancho Cucamonga - Modular Project (Project) budget is comprised of the following components:
|
Design |
$87,000 |
|
Materials Testing/ Inspection |
$42,000 |
|
Project Management |
$85,000 |
|
Construction |
$258,400 |
|
Construction Contingency |
$25,840 |
|
Environmental/Permits |
$35,000 |
|
ISD Cabling |
$56,760 |
|
Total Project Budget |
$ 590,000 |
The total Project budget of $590,000 is funded from the Preschool Services Enterprise Capital Fund and is included as part of the 2019-20 Capital Improvement Program (CIP) budget.
BACKGROUND INFORMATION
The recommended action will award a construction contract to Roadway Engineering & Contracting, Inc., for the Project, which will provide a 648 square foot modular building for office and restroom uses associated with the existing facility. The new building will provide the disabled access that is lacking in the rest of the facility. Project scope will include updated disabled parking and path of travel to the new building for County Preschool services on existing Housing Authority property. The Project will provide for upgraded facilities and accessibility compliance with Americans with Disabilities Act requirements thereby meeting the County and Chief Executive Officer Goals and Objective to Improve County Government Operations and Operate in a Fiscally-Responsible and Business-Like Manner.
On December 17, 2019 (Item No. 56) the Board of Supervisors (Board) found that the Project is exempt under California Environmental Quality Act (CEQA) Guidelines, Section 15301, subsection (e)(2)(B) - Additions to Existing Facilities, and directed the Clerk of the Board to file and post the Notice of Exemption for the Project.
This Project is consistent with County Administrative Office approved CIP Request No. 18-136.
PROCUREMENT
On December 17, 2019 (Item No. 56), the Board authorized the Real Estate Services Department - Project Management (PM) to advertise for competitive bids for the Project. On December 20, 2019, PM advertised in the Daily Press, six plan rooms, PM's website and on the County of San Bernardino's Electronic Procurement Network (ePro). On January 7, 2020, 32 contractors attended a mandatory pre-bid meeting. On January 10, 2020, Addendum No. 1 was issued which revised the bid closing date from February 5, 2020 at 1:00 p.m. to February 13, 2020 at 1:00 p.m., modified the bid documents, and added project drawings and specifications. On February 6, 2020, Addendum No. 2 was issued, which provided response to contractors’ request for additional information.
On February 13, 2020, the following six bids were received.
|
Contractor |
Location |
Bid |
|
Michel Feghali (dba) SPAREA |
Rancho Cucamonga, CA |
Non-Responsive |
|
Roadway Engineering & Contracting, Inc. |
Fontana, CA |
$ 258,400 |
|
Reed Family Enterprises Inc. |
Temecula, CA |
$ 323,238 |
|
Atom Engineering Construction, Inc. |
Hemet, CA |
$ 354,962 |
|
Jergensen Construction |
Oak Hills, CA |
$ 359,600 |
|
Dalke & Sons Construction, Inc. |
Riverside, CA |
$ 465,890 |
Review of bid submissions revealed that Michel Feghali (dba) SPAREA failed to include a base bid amount in its bid proposal as required by the Bid Proposal; PM therefore recommends this bid proposal be deemed nonresponsive. The department did not receive any appeals for this project. PM further recommends the Board award the construction contract to Roadway Engineering & Contracting, Inc., the lowest responsive and responsible bidder.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5437) on February 27, 2020; Preschool Services (Phalos Haire, Interim Director, 383-2005) on February 27, 2020; Purchasing Department (Bruce Cole, Staff Analyst II, 387-2148) on February 27, 2019; Project Management (Jennifer Costa, Assistant Director, 387-5000) on February 27, 2020; Finance (Wen Mai, Principal Administrative Analyst, 387-4020) on March 3, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on March 8, 2020.
(MM: 531-1582)