Legislation Details

File #: 8949   
Type: Consent Status: Passed
File created: 10/13/2023 Department: Board Governed County Service Areas
On agenda: 10/24/2023 Final action: 10/24/2023
Subject: Construction Contract and Related Actions for the County Service Area 70 R-50 Mercury Way Road Rehabilitation Project in the Crestline Area
Attachments: 1. CON-BGCSA-102423 CSA 70 R-50 Mercury Way Contract Award to S. Porter Inc., 2. R1-CON-BGCSA-102423 CSA 70 R-50 Mercury Way Contract Amendment, 3. Item #74 Executed BAI, 4. 23-1182 Executed Contract, 5. 23-1182 A1 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF BOARD GOVERNED COUNTY SERVICE AREAS

AND RECORD OF ACTION

 

                                          October 24, 2023

 

FROM

BRENDON BIGGS, Director, Department of Public Works - Special Districts 

         

SUBJECT                      

Title                     

Construction Contract and Related Actions for the County Service Area 70 R-50 Mercury Way Road Rehabilitation Project in the Crestline Area

End

 

RECOMMENDATION(S)

Recommendation

Acting as the governing body of County Service Area 70 R-50 Mercury Way:

1.                     Award a construction contract to S. Porter, Inc. in the amount of $171,873 for the County Service Area 70 R-50 Mercury Way Road Rehabilitation Project in the Crestline area.

2.                     Approve Amendment No. 1 to the construction contract with S. Porter, Inc. for the County Service Area 70 R-50 Mercury Way Road Rehabilitation Project in the Crestline area, reducing the contract amount by $39,675, from $171,873 to $132,198, with no other changes to the contract.

3.                     Authorize a contingency fund of $13,200 for the County Service Area 70 R-50 Mercury Way Road Rehabilitation Project in the Crestline area.

4.                     Authorize the Director of the Department of Public Works to approve expenditures from the contingency fund in the aggregate amount of $13,200 for verified quantity overruns for this unit priced construction contract with S. Porter, Inc.

5.                     Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the construction contract with S. Porter, Inc. for the total not-to-exceed amount of $13,200, pursuant to Public Contract Code Section 20142.

6.                     Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.

7.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post the budget adjustments, as detailed in the Financial Impact section, for the County Service Area 70 R-50 Mercury Way Road Rehabilitation Project in the Crestline area (Four votes required).

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Operate in a Fiscally-Responsible and Business-Like Manner.

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The County Service Area 70 R-50 Mercury Way (CSA 70 R-50) Road Rehabilitation Project (Project), which includes $132,198 for the amended cost of the construction contract with S. Porter, Inc. and $13,200 for the Project’s contingency fund, is being funded by a loan from the County Service Area Revolving Loan Fund as approved by the Board of Supervisors (Board) on July 12, 2022 (Item No. 49).

 

The Project is partially budgeted in 2023-24 at $75,718, as it was anticipated the Project would commence in 2022-23. However, since the Project did not commence as anticipated, the following 2023-24 budget adjustments are needed to proceed with the Project:

 

Fund Center/Fund

Commitment Item

 Description

Action

Amount

1050003604

54104010

Improvements to Land

Increase

$75,717

3604

37008880

Fund Balance - Available Reserves

Decrease

$75,717

 

BACKGROUND INFORMATION

On July 12, 2022 (Item No. 49), the Board approved the formation of CSA 70 R-50 to provide road maintenance and snow removal services on approximately 1,800 linear feet of paved road on Mercury Way in the Crestline area. At the same time, the Board approved the Project in the amount of $151,435, which consists of pulverizing and repaving approximately 18,388 square feet of existing asphalt road surfaces along Mercury Way, between Skyland Drive to the North and South.

 

This item seeks Board approval to award a construction contract for the Project in the amount of $171,873. However, this item also seeks approval of Amendment No. 1 (Amendment) to immediately reduce the contract amount by $39,675, from $171,873 to $132,198, with no changes to the original contract time nor the Project’s scope. The Amendment is needed for the Project to be constructed within the available funding limits and completed before the winter season arrives. S. Porter, Inc. agreed to lower the cost of material to assist with CSA 70 R-50’s budget constraints, allowing the Project to proceed.

 

Staff of the Department of Public Works - Special Districts (Department) reviewed the Project and determined that a categorical exemption exists in accordance with the California Environmental Quality Act (CEQA) Guidelines, Section 15301(a), Class 1, Existing Facilities. The Class 1 exemption allows for operation, repair, maintenance, involving negligible or no expansion of use beyond that existing at the time of the lead agency's determination but not limited to: existing highways and streets. The Notice of Exemption was filed and posted on August 25, 2023, with the Clerk of the Board of Supervisors.

 

PROCUREMENT

On August 21, 2023, the Department advertised the Project’s plans and specifications in the County’s Electronic Procurement Network (e-Pro) (Bid No. SPD124-SPDAD-5086) in accordance with Public Contract Code Section 22037. On September 12, 2023, the following bids were received:

 

Contractor Name

Bid Amount

S. Porter, Inc.

$171,873

Pave West, Inc.

$185,184

Altmeyer, Inc.

$197,378

Hardy & Harper, Inc.

$415,000

 

The Department reviewed the bids and determined that all were responsive. The Department recommends that the Board award the construction contract to S. Porter, Inc., as the lowest responsive and responsible bidder.  No appeal/protest letters were received.

 

The Project will have a contingency fund of $13,200 (10% of the original contract amount of $132,198) to compensate the contractor (S. Porter, Inc.) for verified quantity overruns, as well as changes in the contract under certain circumstances.  Under an established formula and based on the contract amount of $132,198, Public Contract Code section 20142 allows the Board to authorize the Director of the Department of Public Works to order changes in the contract, including for unforeseen conditions or design shortfalls, should they become necessary in the future, for a total amount not-to-exceed $13,200.

 

Upon Board approval of this item, construction is expected to commence in November 2023 and be completed by December 2023.

 

REVIEW BY OTHERS

This item has been reviewed by Auditor-Controller/Treasurer/Tax Collector (Charlene Huang, Auditor-Controller Manager, 382-7022) on September 25, 2023; County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on October 6, 2023; Purchasing (Jason Cloninger, Buyer, 387-9258) on September 22, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635) on October 6, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on October 6, 2023.