REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
August 5, 2025
FROM
BRADY GERGOVICH, Agricultural Commissioner/Sealer, Department of Agriculture/ Weights & Measures
DON DAY, Director, Project and Facilities Management Department
SUBJECT
Title
Capital Improvement Program Project for the Department of AWM Restroom Revitalization Project
End
RECOMMENDATION(S)
Recommendation
1. Approve Capital Improvement Program Project, in the amount of $223,920, for the AWM Restroom Revitalization Project in the building located at 777 E. Rialto Avenue, in San Bernardino.
2. Authorize the Auditor-Controller/Treasurer/Tax Collector to post the necessary budget adjustments to the Project and Facilities Management Department 2025-2026 budget, as detailed in the Financial Impact section (Four votes required).
(Presenter: Brady Gergovich, Agricultural Commissioner / Sealer, 387-2115)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The AWM Restroom Revitalization Project (WBSE 10.10.1917) (Project) will be funded by reallocating $223,920 from funds originally designated for Agriculture / Weights & Measures's (AWM) Capital Improvement Program Project No. 22-141 AWM for Installation of Parking Cover (WBSE 10.10.1305).
This item authorizes the Auditor-Controller/Treasurer/Tax Collector to post adjustments to the Capital Improvement Program 2025-26 budget:
Fund Center
Commitment Item
Description
Action
Amount
WBSE
7700003100
54304030
Structures & Improvements to Structure
Decrease
$223,920
10.10.1305
7700003100
40909999
Residual Equity Transfers Out
Decrease
$223,920
10.10.1305
7700003100
54304030
Structures & Improvements to Structure
Increase
$223,920
10.10.1917
7700003100
40909995
Residual Equity Transfers In
Increase
$223,...