REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
December 16, 2025
FROM
DON DAY, Director, Project and Facilities Management Department SHANNON D. DICUS, Sheriff/Coroner/Public Administrator
SUBJECT
Title
Amendment and Change Order to Construction Contracts with Griffith Company for the Sheriff/Coroner/Public Administrator's Emergency Vehicle Operations Center Asphalt and Lighting Replacement Project
End
RECOMMENDATION(S)
Recommendation
1. Approve Amendment No. 2 to Contract No. 24-690 with Griffith Company, increasing the total contract amount by $722,380, from $7,946,432 to $8,668,812, and extending the contract term by 119 days, from 365 days to 484 days for the Sheriff/Coroner/Public Administrator's Emergency Vehicle Operations Center Asphalt and Lighting Replacement Project located at 18958 Institution Road in San Bernardino (Four votes required).
2. Approve Change Order No. 2 to Contract No. 24-690 with Griffith Company, increasing the total contract amount by $37,644.36, from $8,668,812 to $8,706,456.36, with no change to the term of 484 days for the Sheriff/Coroner/Public Administrator's Emergency Vehicle Operations Center Asphalt and Lighting Replacement Project located at 18958 Institution Road in San Bernardino (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Sheriff/Coroner/Public Administrator's (Sheriff) Emergency Vehicle Operations Center (EVOC) Asphalt and Lighting Replacement Project (Project) (WBSE 10.10.1222) with a total budget of $14,851,355 is funded from $7,961,232 in Discretionary General Funding and $6,890,768 from Proposition 172 funds, as approved by th...
Click here for full text