Subject: Advertise for Competitive Bids for the 800MHz Upgrade Skyland Peak Tower Project in Crestline
Attachments: 1. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Bid Docs, 2. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Special Conditions, 3. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 1 of 7, 4. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 2 of 7, 5. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 3 of 7, 6. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 4 of 7, 7. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 5 of 7, 8. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 6 of 7, 9. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Plans 7 of 7, 10. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Appendix F & G, 11. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-Asbestos Testing, 12. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-BSK Geotechnical Report, 13. ATT-PFMD-102224-Advertise for Bid-800MHz Upgrade Skyland Peak Tower-SCE WO MAP, 14. Item #32 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

October 22, 2024

FROM
DON DAY, Director, Project and Facilities Management Department
LYNN FYHRLUND, Chief Information Officer, Innovation and Technology Department

SUBJECT
Title
Advertise for Competitive Bids for the 800MHz Upgrade Skyland Peak Tower Project in Crestline
End

RECOMMENDATION(S)
Recommendation
1. Find that the 800MHz Upgrade Skyland Peak Tower Project is exempt under the California Environmental Quality Act Guidelines, Section 15301 (e), Class 1, Existing Facilities.
2. Approve plans and specifications for the 800MHz Upgrade Skyland Peak Tower Project located in Crestline.
3. Authorize the Director of the Project and Facilities Management Department to advertise for competitive bids for the 800MHz Upgrade Skyland Peak Tower Project.
4. Direct the Project and Facilities Management Department to file the Notice of Exemption in accordance with the California Environmental Quality Act.
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of the bid documents and the solicitation of competitive bids will not result in the use of Discretionary General Funding (Net County Cost). The 800MHz Upgrade Skyland Peak Tower Project's (Project) budget of $1,526,000 is funded from the 800MHz Program (WBSE 10.10.0009) as approved by the Board of Supervisors (Board) as part of the 2024-25 Capital Improvement Program (CIP) budget (WBSE 10.10.1237).

BACKGROUND INFORMATION
Approval of this item will allow the Project and Facilities Management Department (PFMD) to solicit competitive bids for the Project located in Crestline. The Project scope of work includes installation of a single self-supporting steel lattice 80-foot tower, new ice bridge, demolition and replac...