File #: 12698   
Type: Consent Status: Passed
File created: 8/11/2025 Department: Public Works-Transportation
On agenda: 8/19/2025 Final action: 8/19/2025
Subject: Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List and Expenditures Strategy
Attachments: 1. ATT-PW-Trans-8-19-25- Road List- Measure I Local Street Pass-Thru 5 year CIP Project List- Attachment A, 2. RES-PW-Trans-8-19-25 Measure I Local Street Pass-Thru 5 Year CIP_Resolution, 3. ATT-PW-Trans-8-19-25- Expenditure Strategy- Measure I Local Street Pass-Thru 5 year CIP Project List- Attachment B, 4. ADD-ATT-PW-Trans-8-19-25 Template- Measure I Local Street Pass-Thru 5 Year CIP Project List 1, 5. Item #50 Executed BAI, 6. 2025-188 Executed Resolution
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 19, 2025

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List and Expenditures Strategy
End

RECOMMENDATION(S)
Recommendation
Adopt Resolution approving the Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List and the Expenditure Strategy for 2025-26 through 2029-30.
(Presenter: Byanka Velasco, Assistant Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost) or cost to the Department of Public Works (Department). The Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan (Plan) Project List identifies projects assigned to utilize current and future Measure "I" sales tax revenues. Sufficient appropriation and revenue for continuing projects are included in the Department's 2025-26 Transportation Budget and will be included in future recommended budgets. Adjustments to the 2025-26 budget for new projects are not requested at this time but will be included in a future budget report, which will be presented to the Board of Supervisors (Board) for approval as necessary.

BACKGROUND INFORMATION
Adoption of the Resolution approves the Plan project list from 2025-26 to 2029-30 (Attachment A) and the Expenditure Strategy (Attachment B). The Plan allocates funding to six subareas of the County: the Colorado River, Morongo Basin, North Desert, San Bernardino Mountains, San Bernardino Valley, and Victor Valley. These funds ...

Click here for full text