REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION
November 5, 2024
FROM
NOEL CASTILLO, Chief Flood Control Engineer, Flood Control District
SUBJECT
Title
Amendment to Contract with WEST Consultants, Inc. for San Bernardino County Hydrology Manual and Detention Basin Design Criteria Update
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District, approve Amendment No. 1 to Contract No. 23-25 with WEST Consultants, Inc., for professional civil engineering services to update the San Bernardino County Hydrology Manual and Detention Basin Design Criteria, extending the term of the contract by one year, for a new total term of January 24, 2023, to January 23, 2026, with no change to the contract amount of $1,141,242.
(Presenter: Noel Castillo, Chief Flood Control Engineer, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The San Bernardino County Flood Control District (District) is funded by property taxes, fee revenue, and other local, state, and federal funding. Amendment No. 1 (Amendment) to Contract No. 23-25 (Contract) with WEST Consultants, Inc. (WEST) will not impact the District's finances. The total contract amount of $1,141,242 is funded with property tax revenue. Sufficient appropriation and revenue have been included in the District's 2024-25 budget (1970002510-FL0115) and will be included in future recommended budgets.
BACKGROUND INFORMATION
The District's first San Bernardino County Hydrology Manual (Hydrology Manual) was released in May 1983 and updated in August 1986. In September 1987, the District issued Detention Basin Design Criteria to...