Skip to main content
File #: 8149   
Type: Consent Status: Passed
File created: 6/5/2023 Department: Public Works-Transportation
On agenda: 6/13/2023 Final action: 6/13/2023
Subject: Acceptance of Highway Safety Improvement Program Grant Funds for Construction of Safety Improvements
Attachments: 1. ADD-ATT-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Award Letter Cajon Pass, 2. ADD-ATT-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Award Letter Curved Mountain Roads, 3. ADD-ATT-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Award Letter Rural Intersection, 4. ADD-ATT-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Award Letter Rural Road, 5. COV-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Cajon Pass, 6. COV-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Curved Mountain Roads, 7. COV-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Rural Intersection, 8. COV-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements - Rural Road, 9. EXH-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements, 10. MAP-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements, 11. R3-BAI-PW-Trans 6-13-23 Accept HSIP Funds for Construction of Safety Improvements, 12. Item #65 Executed BAI, 13. 23-530 Executed Contract, 14. 23-531 Executed Contract, 15. 23-532 Executed Contract, 16. 23-533 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

June 13, 2023

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
Acceptance of Highway Safety Improvement Program Grant Funds for Construction of Safety Improvements
End

RECOMMENDATION(S)
Recommendation
1. Accept Highway Safety Improvement Program grant funds, in the amount of $4,994,830, from the California Department of Transportation for Rural Road Systemic Safety Improvements at various locations throughout San Bernardino County.
2. Accept Highway Safety Improvement Program grant funds, in the amount of $1,252,800, from the California Department of Transportation for Rural Intersection Systemic Safety Improvements at various locations throughout San Bernardino County.
3. Accept Highway Safety Improvement Program grant funds, in the amount of $1,183,050, from the California Department of Transportation for Cajon Pass Safety Improvements on Cajon Boulevard, in the Devore area.
4. Accept Highway Safety Improvement Program grant funds, in the amount of $2,569,320, from the California Department of Transportation for Curved Mountain Roads Systemic Safety Improvements at various locations throughout San Bernardino County.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Department of Public Works (Department) is funded by gas tax revenue, fee revenue, and other state and local funding. The total estimated cost for all four projects is $11,544,600, which will be funded by the grant award from the California Department of Transportation (Caltrans) of $10,000,000, and gas tax revenue of $1,544,600 for the req...

Click here for full text