Skip to main content
File #: 13908   
Type: Consent Status: Passed
File created: 3/30/2026 Department: Project and Facilities Management
On agenda: 4/7/2026 Final action: 4/7/2026
Subject: Amendment to Construction Contract with Rasmussen Brothers Construction, Inc., for the Prado Tent Campground Restroom Addition Project
Attachments: 1. R1-CON-PFMD-040726-Amendment No. 1-Prado Tent Campground Restroom Addition
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

April 7, 2026

FROM
MOE YOUSIF, Interim Director, Project and Facilities Management Department
BEAHTA R. DAVIS, Director, Regional Parks Department

SUBJECT
Title
Amendment to Construction Contract with Rasmussen Brothers Construction, Inc., for the Prado Tent Campground Restroom Addition Project
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Contract No. 24-979 with Rasmussen Brothers Construction, Inc., increasing the total contract amount by $127,902, from $715,000 to $842,902, and extending the construction completion date by 91 days, from January 9, 2026 to April 10, 2026, for the Prado Tent Campground Restroom Addition Project in Chino (Four votes required).
(Presenter: Moe Yousif, Interim Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Promote and Fulfill the Countywide Vision.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The contract amendment in the amount of $127,902 is within the Prado Tent Campground Restroom Addition (Project) (WBSE No. 10.10.1396) project budget of $1,394,655. The budget consists of $544,655 in American Rescue Plan Act funds and $850,000 in Federal Earmark funds as approved by the Board of Supervisors of June 10, 2025 (Item No. 136).

The Project is comprised of the following components:

Description
Amount
Project Design
$185,465
Project Management, Inspection, and Testing
$315,440
Construction
$715,000
Construction Contingency
$50,848
Amendment No. 1
$127,902
Total Project Budget
$1,394,655

BACKGROUND INFORMATION
The Prado Regional Park tent campground does not have any restrooms or showers, and the distance to the closest available restrooms and showers exceeds the travel requirements of the American with Disabilit...

Click here for full text