Skip to main content
File #: 13381   
Type: Consent Status: Agenda Ready
File created: 12/8/2025 Department: Project and Facilities Management
On agenda: 12/16/2025 Final action:
Subject: Amendment and Change Order to Construction Contract with Dalke & Sons Construction, Inc. for the Sheriff Scientific Investigations Division Orange and Blue Labs Remodel Project
Attachments: 1. CON-PFMD-121625-Amendment-Dalke Sons Construction -Sheriff SID Orange & Blue Labs Remodel Project, 2. CON-PFMD-121625-Change Order-Dalke Sons Construction -Sheriff SID Orange & Blue Labs Remodel Project
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

December 16, 2025

FROM
DON DAY, Director, Project and Facilities Management Department SHANNON D. DICUS, Sheriff/Coroner/Public Administrator

SUBJECT
Title
Amendment and Change Order to Construction Contract with Dalke & Sons Construction, Inc. for the Sheriff Scientific Investigations Division Orange and Blue Labs Remodel Project
End

RECOMMENDATION(S)
Recommendation
1. Approve Amendment No. 1 to Contract No. 25-101 with Dalke & Sons Construction, Inc., for the Sheriff Scientific Investigations Division Orange and Blue Labs Remodel Project in San Bernardino, increasing the total contract amount by $179,318.37, from $6,692,000 to $6,871,318.37, and extending the construction completion date by an additional 58 days, from March 3, 2026, to April 30, 2026. (Four votes required).
2. Approve Change Order No. 1 to Contract No. 25-101 with Dalke & Sons Construction, Inc., for the Sheriff Scientific Investigations Division Orange and Blue Labs Remodel Project in San Bernardino, increasing the total contract amount by $21,990.12, from $6,871,318.37 to $6,893,308.49, with no change to the construction completion date of April 30, 2026. (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Sheriff/Coroner/Public Administrator's (Sheriff) Scientific Investigations Division (SID) Orange and Blue Labs Remodel Project (Project) (WBSE 10.10.1493) with a total budget of $8,561,120 is funded with Proposition 172 funds. The Project was approved by the Board of Supervisors (Board) on June 10, 2025 (Item No. 136) as part of the 2025-26 Capital Improvement Program...

Click here for full text