Skip to main content
File #: 11552   
Type: Consent Status: Passed
File created: 1/14/2025 Department: Real Estate Services
On agenda: 1/28/2025 Final action: 1/28/2025
Subject: Waiver Valuations and Acquisition Agreements for Road Easements for the Blake Street and Other Roads Project in the Unincorporated Area of Muscoy
Attachments: 1. R1-COV-RESD-DPW-012825-Valuation and Acquisition Blake Street and Other Roads ADA Ramps Project, 2. R1-ATT-RESD-DPW-T-012825-Valuation and Acquisition Blake Street and Other Roads ADA Ramps Project-Acquisitions Agreement Template, 3. BAI-RESD-DPW-T-012825-Valuation and Acquisition Blake Street and Other Roads ADA Ramps Project.Redline, 4. ATT-RESD-DPW-T-012825-Valuation and Acquisition Blake Street and Other Roads ADA Ramps Project-Acquisitions Agreement Template.Redline, 5. Item #49 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

January 28, 2025

FROM
TERRY W. THOMPSON, Director, Real Estate Services Department
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Waiver Valuations and Acquisition Agreements for Road Easements for the Blake Street and Other Roads Project in the Unincorporated Area of Muscoy
End

RECOMMENDATION(S)
Recommendation
1. Approve Waiver Valuation Nos. 24-101 and 24-102, copies of which are on file with the Real Estate Services Department.
2. Authorize the acquisition of two road easements from two property owners over portions of certain real properties, totaling approximately 468 square feet, for the Blake Street and Other Roads Project in the unincorporated area of Muscoy, at a total cost not to exceed $5,300, which includes the just compensation and a contingency amount of up to $1,000 for each property owner.
3. Approve the form of Acquisition Agreement to acquire two road easements from two property owners for the Blake Street and Other Roads Project in the unincorporated area of Muscoy.
4. Authorize the Director of the Real Estate Services Department to:
a. Complete and execute two Acquisition Agreements, in substantial conformance with the approved form of Acquisition Agreement, to acquire two road easements from two property owners over portions of certain real properties, totaling approximately 468 square feet, for the Blake Street and Other Roads Project in the unincorporated area of Muscoy, at a total cost not to exceed $5,300, which includes the just compensation and a contingency amount of up to $1,000 for each property owner.
b. Execute any other non-substantive documents necessary to complete these transactions, subject to County Counsel review.

(Presenter: Terry W. Thompson, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced,...