Legislation Details

File #: 706   
Type: Consent Status: Passed
File created: 7/16/2019 Department: Public Works-Transportation
On agenda: 7/23/2019 Final action: 7/23/2019
Subject: Plans and Specifications for Pavement Rehabilitation on Philadelphia Street, in the Chino Area
Attachments: 1. ATT-PW-Trans 7-23-19 Plans and Specs for Pavement Rehab on Philadelphia Street, Chino - Plans, 2. ATT-PW-Trans 7-23-19 Plans and Specs for Pavement Rehab on Philadelphia Street, Chino - Specs, 3. MAP-PW-Trans 7-23-19 Plans and Specs for Pavement Rehab on Philadelphia Street, Chino, 4. Item#31 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

July 23, 2019

 

FROM

KEVIN BLAKESLEE, Director, Department of Public Works - Transportation

         

SUBJECT                      

Title                     

Plans and Specifications for Pavement Rehabilitation on Philadelphia Street, in the Chino Area

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve plans and specifications for the pavement rehabilitation on Philadelphia Street from the Los Angeles County line east to Norton Avenue, in the Chino area (Project), as signed and sealed by a registered civil engineer.

2.                     Authorize the Director of Public Works to advertise the Project for bids.

(Presenter: Kevin Blakeslee, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Department of Public Works (County) is funded by Gas Tax revenues, fees, and other state and local funding. The Project will be funded with Senate Bill 1 Road Maintenance and Rehabilitation Account (RMRA) funds. In accordance with Cooperative Agreement 17-112, the City of Chino (City) agrees to reimburse the County for its estimated share of the Project.  Sufficient appropriation is included in the 2019-20 Road Operations budget (6650002000 34H14857).

 

BACKGROUND INFORMATION

The Project is located on Philadelphia Street from the Los Angeles County line east to Norton Avenue with portions within the City, approximately 0.97 miles in length. The Project consists of pavement rehabilitation and upgrading certain pedestrian curb ramps to comply with the current Americans with Disabilities Act (ADA) guidelines. The Project also includes a small segment of road widening with the installation of curb, gutter, and sidewalk. The Project aligns with the County and Chief Executive Officer’s goals and objectives to ensure the development of a well-planned, balanced, and sustainable County and providing for the safety of County residents by improving the structural integrity of the existing roadway, improving access for all pedestrians and removing architectural barriers for those with mobility disabilities.  All work for the Project will be done within the existing road right-of-way.

The Project’s specifications include an allowance, for the amount of $25,000, for differing site conditions associated with utilities and $25,000 for potential design changes for the curb ramps within the City for a total of $50,000.

 

On March 7, 2017 (Item No. 36), the Board of Supervisors (Board) approved Cooperative Agreement No. 17-112 between the County and the City for reimbursement of the City’s share of construction costs for the Project, determined that the Project was exempt under the California Environmental Quality Act (CEQA), approved the Project as defined in the Notice of Exemption, and directed the Clerk of the Board to file and post said notice.

 

PROCUREMENT

The Project will be advertised for bids in accordance with section 22037 of the California Public Contract Code.  The Department anticipates returning to the Board for an award of contract in September 2019.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Suzanne Bryant, Deputy County Counsel, 387-5455) on June 12, 2019; Finance (Wen Mai, Administrative Analyst, 387-4020) on June 14, 2019; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on June 23, 2019.