REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
December 17, 2019
FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management Division
SUBJECT
Title V
Amendment No. 1 to Construction Contract with Abboud Diamond Construction, Inc. for Onyx Peak Solar Upgrade Project
End
RECOMMENDATION(S)
Recommendation
1. Approve a $521,000 increase in the project budget, from $470,000 to $991,000, for the Onyx Peak Solar Upgrade Project (10.10.0175) located at Onyx Peak, Big Bear (APN 0305-201-05).
2. Approve Amendment No. 1 to Contract No. 15-445 with Diamond Construction, Inc. in the amount of $498,749 increasing the construction contract from $248,729 to a total of $747,478, and extending the contract end date from October 2, 2019 to April 10, 2020 for the Onyx Peak Solar Upgrade Project (10.10.0175) located at Onyx Peak, Big Bear (APN 0305-201-05) (Four Votes required).
3. Authorize the Auditor-Controller/Treasure/Tax Collector to adjust appropriation within the Capital Improvement Program (CIP), as detailed in the Financial Impact Section, transferring $521,000 from the 800 MHz Radio Replacement Project (10.10.0009) to the Onyx Peak Solar Upgrade Project (10.10.0175) increasing the total project budget from $470,000 to $991,000 (Four Votes required).
(Presenter: Terry W. Thompson, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The project budget of $991,000 is comprised of the following components:
Project Design
$40,000
Project Management, Inspection and Testing
$156,398
Construction
$747,478
Construction Contingency
$47,124
Total Project Budget
$991,000
The proposed funding source for the ...