SUBJECT
Title
Amendment to Construction Contract with Cora Constructors, Inc., for the Lake Gregory San Moritz Prefabricated Restroom Project
End
RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Construction Contract No. 24-931 with Cora Constructors, Inc., for the Lake Gregory San Moritz Prefabricated Restroom Project in Crestline, adding to the scope of work, increasing the total contract amount by $43,888, from $410,000 to $453,888, and extending the final completion date by 27 days, from October 25, 2025 to November 21, 2025 (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The contract increase of $43,888 is within the total Project budget. The Lake Gregory San Moritz Prefabricated Restroom Project (Project) (WBSE 10.10.1398), budget of $1,551,600, was approved by the Board of Supervisors (Board) as part of the 2025-26 Capital Improvement Program (CIP) Budget on June 10, 2025 (Item No. 136).
BACKGROUND INFORMATION
On September 24, 2024 (Item No. 52), as the result of Request for Proposals No. ANE223-ANE2C-5409, the Board awarded Construction Contract No. 24-931 (Contract) to Cora Constructors, Inc., in the amount of $410,000, for a contract period of 365 calendar days from the date of the issuance of the Notice to Proceed for the Project.
Approval of Amendment No. 1 (Amendment) to the Contract, in the amount of $43,888, will cover unanticipated costs due to unforeseen site conditions. The changes in...