REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
October 24, 2023
FROM
BRENDON BIGGS, Director, Department of Public Works - Special Districts
SUBJECT
Title
Grant Application to the Southern California Association of Governments for the Bloomington Sewer Expansion Project
End
RECOMMENDATION(S)
Recommendation
1. Approve and authorize the submission of a Regional Utilities Supporting Housing grant application to the Southern California Association of Governments requesting an amount not-to-exceed $6,500,000 for the Bloomington Sewer Expansion Project.
2. Authorize the Chair of the Board of Supervisors, Chief Executive Officer, or Director of the Department of Public Works to execute and submit all documents, including the application and any other subsequent documents or amendments, that are related to the Regional Utilities Supporting Housing grant application process, subject to review by County Counsel.
3. Direct the Director of the Department of Public Works to transmit the Regional Utilities Supporting Housing grant application and amendments to the Clerk of the Board of Supervisors within 30 days of execution.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Department of Public Works - Special Districts (Department) is seeking a grant in the amount of $6,500,000 from the Southern California Association of Governments (SCAG) for the Bloomington Sewer Expansion Project (Project). If the application process is successful, the Department will return to the Board of Supervisors for acceptance of the grant funds in accordance with County Policy 05-13. This grant has no required matching component.
BACKGROUND INFORMATION
The Department is requesting approval for the submission of a grant application to SCAG, requesting $6,500,000 for the Project. The Project proposes to extend the existing sewer infrastructure within the Bloomington community to support future housing development and will include the installation of sewer main line and manholes. More specifically, the improvements include 4,970 linear feet (LF) of eight-inch sewer main, 2,600 LF of 12-inch sewer main, and 24 manholes. The deadline for submitting this application to SCAG is November 6, 2023.
Authorization is requested for the Chair of the Board of Supervisors, the Chief Executive Officer, or the Director of the Department of Public Works to take any actions needed in relation to the grant application process and to sign and execute any documents required for the grant application. The grant application guideline was released on September 11, 2023, and provided a short application deadline of November 6, 2023. Therefore, the authorization provided by Recommendation No. 2 is needed to allow the Department to work within the grantor’s required timelines for completion and submission of the grant application.
PROCUREMENT
Not applicable.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on October 2, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635) on October 3, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on October 5, 2023.