San Bernardino header
File #: 10730   
Type: Consent Status: Passed
File created: 8/13/2024 Department: Project and Facilities Management
On agenda: 8/20/2024 Final action: 8/20/2024
Subject: Construction Contract with Rasmussen Brother Construction, Inc. for Prado Front Gate Renovation Project in Chino
Attachments: 1. ADD-CON-PFMD-082024-Construction Contract-Rasmussen Brother Construction, Inc-Prado Front Gate Renovation Project, 2. ATT-PFMD-082024-Construction Contract-Rasmussen Brother Construction, Inc-Prado Front Gate Renovation Project-Addendum No. 1, 3. ATT-PFMD-082024-Construction Contract-Rasmussen Brother Construction, Inc-Prado Front Gate Renovation Project-Addendum No. 2, 4. Item #56 Executed BAI, 5. 24-763 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 20, 2024

FROM
DON DAY, Director, Project and Facilities Management Department
BEAHTA DAVIS, Director, Regional Parks Department

SUBJECT
Title
Construction Contract with Rasmussen Brother Construction, Inc. for Prado Front Gate Renovation Project in Chino
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1 to the bid documents dated May 20, 2024, which provided answers to contractor questions for the Prado Front Gate Renovation Project.
2. Approve Addendum No. 2 to the bid documents dated May 28, 2024, which moved the official bid date to June 4, 2024.
3. Approve a $1,967,251 increase in the project budget, increasing the project budget from $1,328,895 to $3,296,146, for the Prado Front Gate Renovation Project (WBSE 10.10.1257) located at 16700 Euclid Ave. in Chino.
4. Award a construction contract to Rasmussen Brother Construction, Inc., in the amount of $2,325,000, for a contract period of 548 calendar days from the date of issuance of the Notice to Proceed for Prado Front Gate Renovation Project.
5. Authorize the Director of the Project and Facilities Management Department to order and execute any necessary changes or additions in the work being performed under the contract referenced in Recommendation No. 4 for a total amount not to exceed $128,750, pursuant to Public Contract Code Section 20142.
6. Authorize the Director of the Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.
7. Authorize the Auditor-Controller/Treasure/Tax collector to post the necessary budget adjustments within the Capital Improvement Program in 2024-25, as detailed in the Financial Impact section (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscal...

Click here for full text