REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT

AND RECORD OF ACTION

 

December 15, 2020

 

FROM

BRENDON BIGGS, Chief Flood Control Engineer, Flood Control District

BEAHTA DAVIS, Director, Regional Parks Department  

 

SUBJECT

Title

Memorandum of Understanding between San Bernardino County Flood Control District and County of San Bernardino for Maintenance Activities and Stockpiling

End

 

RECOMMENDATION(S)

Recommendation

1.                     Acting as the governing body of the San Bernardino County Flood Control District:

a.                     Terminate Agreement No. 12-471 with the County of San Bernardino for maintenance services at Regional Parks with an indefinite term.

b.                     Approve Memorandum of Understanding with the County of San Bernardino for maintenance activities at Regional Parks and stockpiling at Yucaipa Regional Park for a term of December 15, 2020 through June 30, 2025 with an option to extend the term for up to two additional five-year periods.

2.                     Acting as the governing body of the County of San Bernardino:

a.                     Terminate Agreement No. 12-471 with the San Bernardino County Flood Control District for maintenance services at Regional parks for an indefinite term.

b.                     Approve Memorandum of Understanding with the San Bernardino County Flood Control District for maintenance activities at Regional Parks and stockpiling at Yucaipa Regional Park for a term of December 15, 2020 to June 30, 2025 with an option to extend the term for up to two additional five-year periods.

 

(Presenter: Melissa Walker, Deputy Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Operate in a Fiscally-Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The proposed Memorandum of Understanding (MOU) is non-financial, and allows for the San Bernardino County Flood Control District (District) to use a portion of the Yucaipa Regional Park for stockpiling debris material generated by storms in the El Dorado/Apple burn scar area. In exchange for the ability to stockpile, the District will make improvements to the site and conduct maintenance on the access roads. This item will have a positive impact on the District and County of San Bernardino Regional Parks Department (Parks) through reduced maintenance costs by using each other’s existing resources in a more efficient manner when performing maintenance activities on their respective facilities, access roads, and related appurtenances. Sufficient appropriation for maintenance is included in the District’s and Parks’ 2020-21 budget and will be included in future recommended budgets.

 

BACKGROUND INFORMATION

On July 10, 2012 (Item No. 60), the Board of Supervisors (Board) approved Agreement No. 12-471 (2012 Agreement) between the District and Parks under which each could provide mutual maintenance activities to increase efficiency and reduce maintenance costs. The types of work included debris cleanup, repair of fencing, renting of equipment, brush clearing, trail repair, striping, drainage facility maintenance, and general labor work.

 

The 2012 Agreement was in an outdated format and did not include a term end date.  As such, the District and Parks seek to terminate the 2012 Agreement and enter into a new MOU.  The proposed MOU sets forth the same scope of work as the 2012 Agreement as well as allows for the District to use a portion of the Yucaipa Regional Park for stockpiling debris material generated by storms in the El Dorado/Apple burn scar area. In exchange for the ability to stockpile, the District will make improvements to the site and conduct maintenance on the access roads.

 

The term of the proposed MOU is from December 15, 2020, through June 30, 2025, but may be terminated by either party upon 30 days written notice.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Sophie A. Akins and Dawn M. Martin, Deputies County Counsel, 387-5455) on November 17, 2020; Finance (Jessica Trillo, Administrative Analyst, 387-4222; and Elias Duenas, Administrative Analyst, 387-4052) on November 25, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on November 29, 2020.