REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
February 28, 2023
FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation
SUBJECT
Title
Amendment to Cooperative Agreement with the City of San Bernardino for 40th Street and Other Roads Project
End
RECOMMENDATION(S)
Recommendation
1. Approve Amendment No. 1 to Cooperative Agreement No. 20-946 with the City of San Bernardino to increase the estimated contribution amounts from the City of San Bernardino by $425,000, from $490,000 to $915,000, and San Bernardino County by $2,180,000, from $3,020,000 to $5,200,000, for a total increase to the Project of $2,605,000, with no change to the contract period of September 29, 2020 through December 31, 2025.
2. Authorize the Director of the Department of Public Works to increase San Bernardino County’s contribution amount by up to 25 percent, from $5,200,000 to $6,500,000, should Project construction costs dictate such an increase.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The amendment will increase the total estimated cost for the 40th Street and Other Roads Project in the San Bernardino area (Project) by $2,605,000, from $3,510,000 to $6,115,000. The amendment will increase San Bernardino County’s (County) estimated share of the project by $2,180,000, which will be funded with Senate Bill (SB) 1 Road Maintenance and Rehabilitation Account (RMRA) funds. The City of San Bernardino’s (City) estimated share of cost will increase by $425,000. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2022-23 Road Operations budget (6650002000 H14922).
BACKGROUND INFORMATION
The County and City agreed to participate in a joint pavement rehabilitation project covering 3.37 miles of roadways in the San Bernardino area. Other improvements include constructing new or updating curb ramps pursuant to Americans with Disabilities Act (ADA) guidelines. On April 17, 2018 (Item No. 39), the Board of Supervisors (Board) authorized the Project as part of the 2018-19 SB 1 RMRA project list. On September 29, 2020 (Item No. 49), the Board approved Cooperative Agreement No. 20-946 (Agreement) with the City for the Project. Based on the terms of the Agreement, the total Project cost was then estimated to be $3,510,000 with the County and City’s share of the estimated cost being $3,020,000 and $490,000 respectively.
The Project costs have been revised after bid opening on December 15, 2022, where the lowest responsive and responsible bid for the construction contract was $4,431,700. The Agreement provided that the County could award the contract if the lowest responsible bid was higher than the cost estimate, as long as the bid did not exceed the original construction cost estimate by more than 25% of the estimated construction costs. The amount of the lowest responsible bid was over 25% greater than the construction cost of $2,860,000 approved in the Agreement. In addition, the City has subsequently requested that the County extend the limits of the pavement improvements on 40th Street an additional 0.03 miles to the intersection of Third Avenue and 40th Street. The requested extension is solely within the City’s jurisdiction and included in their cost share. Extending the project limits on 40th Street, coupled with construction materials cost increases, such as asphalt and concrete, require the City and County to agree to increase their respective contribution amounts to complete this Project.
Recommendation No. 2 will authorize the Department’s Director to increase the County’s contribution by 25%. Additional costs are anticipated as the lowest responsive and responsible contract bid of $4,431,700 does not include the 10% contingency and the construction management/materials testing cost, which is generally 15% of the construction contract award cost.
Approval of this item will amend the Agreement to increase the parties’ share of costs, as well as require the City to provide a qualified representative to inspect the Project’s construction site as needed. The City approved Amendment No.1 on February 1, 2023. The Project’s construction contract award to Matich Corporation will occur following approval of this item by the Board.
This item meets the County and the Chief Executive Officer’s goals and objectives by allowing the County to continue working with the City to ensure the Project is completed.
PROCUREMENT
Not applicable.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on January 18, 2023; Finance (Carl Lofton, Administrative Analyst, 387-5404) on January 4, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on January 6, 2023.