REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
January 27, 2026
FROM
MOE YOUSIF, Interim Director, Project and Facilities Management Department
SUBJECT
Title
Change Order to Contract with Swinerton Builders, Inc., and Amendment to Construction Management Contract with Griffin Structures, Inc. for the Valley Communication Center Project
End
RECOMMENDATION(S)
Recommendation
1. Approve Change Order No. 3 to Contract No. 23-527 with Swinerton Builders, Inc., increasing the contract amount by $930,098.19, from $98,764,670.30 to $99,694,768.49, and extending the contract completion date from December 1, 2025, to January 28, 2026, for additional work on the Valley Communication Center Project located at 153 South Lena Road in San Bernardino (Four votes required).
2. Approve Amendment No. 1 to Contract No. 21-493, with Griffin Structures, Inc., effective June 22, 2021 for additional scope of work already performed, increasing the not to exceed amount by $292,000, from $4,067,500 to $4,359,500, and exercising both options to extend the contract term by two years, for a total contract period of June 22, 2021, to February 28, 2027, for the Valley Communication Center Project located at 153 South Lena Road in San Bernardino.
(Presenter: Moe Yousif, Interim Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost) or additional costs to the project budget. The Valley Communication Center Project (Project) (WBSE 10.10.0181) has a total budget of $125,582,384, primarily funded by the American Rescue Plan Act (ARPA) and Discretionary General Funding. In accordance with the United States Department of the Treasury's ARPA Final Rule, $106,012,906 of the total Project budget has been ...