OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

December 14, 2021

 

FROM

TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management

         

SUBJECT                      

Title                     

Amendment to Construction Contract with Jergensen Construction, Inc. for the 800 MHz Aerojet - Generator Replacement Project

End

 

RECOMMENDATION

Recommendation

Approve Amendment No. 1 to Contract No. 21-316 with Jergensen Construction, Inc., increasing the Contract total by $18,550, from $143,700 to a total of $162,250, and extending the Contract Time by an additional 91 calendar days, from 210 calendar days to 301 calendar days, with a new construction completion date of April 4, 2022, for the 800 MHz Aerojet - Generator Replacement Project (10.10.0997) located in Chino Hills (Assessor Parcel Number 101726121) (Four votes required).

(Presenter:  Terry W. Thompson, Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of Amendment No. 1 will not result in the use of additional Discretionary General Funding (Net County Cost).  The 800 MHz Aerojet - Generator Replacement Project (Project) budget of $726,302 (10.10.0997) is funded with Discretionary General Funding, previously approved by the Board of Supervisors (Board) as part of the 2011-12 Capital Improvement Program (CIP) Countywide 800 MHz Radio System Upgrade Project and is comprised of the following: 

 

Description

Amount

Investigation and Assessment

$  35,000  

Design

$  76,760    

Testing/Inspection

$  20,000    

Project Management

$  75,000    

Construction

$162,250 

Construction Contingency

$  14,370    

Project Contingency

$342,922    

Total Project Budget

$726,302

 

BACKGROUND INFORMATION

On November 17, 2020 (Item No. 76), the Board authorized the Real Estate Services Department - Project Management to advertise for competitive bids for the Project.  On May 4, 2021 (Item No. 52), the Board awarded contract No. 21-316 to Jergensen Construction Inc. (Jergensen) for the Project.

 

Amendment No. 1 to the Project will increase the contract amount by $18,550 with Jergensen for the additional labor, materials, and equipment required to install a new 25-foot power pole, new 200 Amp can, utility riser conduit, conductor wire, weather head, and fire wrap on the first 8 feet of the new wood pole as requested in Jergensen’s Change Order Request (COR) No. 001 dated August 9, 2021 and COR No. 002 dated October 16, 2021.  The additional scope of work was unforeseen and is required by Southern California Edison.

 

Amendment No. 1 also will extend the Contract Time with Jergensen an additional 91 calendar days, from 210 calendar days to 301 calendar days, to allow for completion of the additional scope of work required by SCE, as well as material shortages caused by the COVID-19 pandemic, included in Amendment No. 1.  The Contract Time is the agreed upon period of time allotted to Jergensen to achieve completion of the entire scope of work without the imposition of liquidated damages.  Extension of the Contract Time is permitted by Section 3.1 of the contract, subject to written approval of the County.  At all times the contract as a whole remains in full force and effect until all issues related to the contract have been resolved.  The original construction completion date was January 3, 2022; the new construction completion date is April 4, 2022.

 

PROCUREMENT

The unanticipated additional cost described above are related to events that took place after the competitive bid process that resulted in the original contract with Jergensen.  Therefore, no additional procurement activities are required.

 

Per Public Contract Code section 20136, Board approval is required for this amendment to the contract with Jergensen.  Purchasing supports the continued use of Jergensen for this project.   

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5455) on October 26, 2021; Innovation and Technology Department (Tim Trager, Chief, Public Safety Communications Division, 388-5563) on October 26, 2021; Purchasing Department (Bruce Cole, Supervising Buyer, 387-2148) on November 3, 2021; Real Estate Services - Project Management (Kevin Ryan, Assistant Director, 387-5000) on November 5, 2021; Real Estate Services Department (Jennifer Costa, Assistant Director, 387-5000) on November 10, 2021; Finance (Wen Mai, Principal Administrative Analyst, 387-4020) on November 23, 2021; and County Finance and Administration (Diana Atkeson, Deputy Executive Officer, 387-5423) on November 23, 2021.

 