REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION
October 24, 2023
FROM
BRENDON BIGGS, Chief Flood Control Engineer, Flood Control District
SUBJECT
Title
Contract with H&H General Contractors, Inc. for the El Rey Avenue Culvert Replacement Project at Twentynine Palms Channel in the City of Twentynine Palms
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District:
1. Approve Addendum No. 1 issued on September 5, 2023, Addendum No. 2 issued on September 12, 2023, and Addendum No. 3 issued on September 13, 2023 to the bid documents for the El Rey Avenue Culvert Replacement Project at Twentynine Palms Channel in the City of Twentynine Palms.
2. Award a contract to H&H General Contractors, Inc. (Highland, CA) in the amount of $1,913,205 for the El Rey Avenue Culvert Replacement Project at Twentynine Palms Channel in the City of Twentynine Palms.
3. Authorize a contingency fund of $191,320 for the El Rey Avenue Culvert Replacement Project at Twentynine Palms Channel in the City of Twentynine Palms.
4. Authorize the Chief Flood Control Engineer of the San Bernardino County Flood Control District to approve the expenditure of the contingency fund of $191,320 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Chief Flood Control Engineer of the San Bernardino County Flood Control District to order any necessary changes or additions in the work being performed under the contract for a total amount not-to-exceed $108,160 of the $191,320 contingency fund, pursuant to Public Contract Code section 21061(d).
6. Authorize the Chief Flood Control Engineer of the San Bernardino County Flood Control District to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Chief Flood Control Engineer, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The El Rey Avenue Culvert Replacement Project at Twentynine Palms Channel in the City of Twentynine Palms (Project) will be funded by the City of Twentynine Palms (City) and San Bernardino County Flood Control District (District) property tax revenue. Sufficient appropriation and revenue for the Project are included in the District’s 2023-24 budget (1960002540 F02749).
BACKGROUND INFORMATION
The Project consists of removing an existing corrugated steel pipe arch culvert and replacing it with a new reinforced concrete box culvert and wing walls. A culvert is a structure, such as a tunnel, that moves a stream under a road, and wing walls are vertical concrete slabs that prevent soil erosion, retain the embankment adjacent to the culvert, and direct the flow of water. The Project also includes reconstructing approximately 200 feet of roadway, sidewalk, curb and gutter, installing handrails, reconstructing drainage inlets, re-grading areas immediately upstream and downstream of the new culvert structure, and constructing rock slope protection.
The Project will be constructed by the District, in part, using funding provided by the City under Cooperative Agreement No. 23-491, approved by the Board of Supervisors (Board) on May 23, 2023 (Item No. 100). The Cooperative Agreement terminates upon the earlier of December 13, 2028 or final completion and final payment.
On May 23, 2023 (Item No. 100), the Board determined the Project was exempt under the California Environmental Quality Act (CEQA), approved the Project as defined in the Notice of Exemption, and directed the Clerk of the Board to file and post said notice. No CEQA challenge was timely filed. Additionally, in 2021, the District applied for and received State regulatory permits from the Colorado River Basin Regional Water Quality Control Board and California Department of Fish and Wildlife, thereby meeting the CEQA and State regulatory permit requirements necessary for Project implementation.
The Project is consistent with the County and the Chief Executive Officer’s goals and objectives to provide for the safety, health, and social service needs of County residents by conveying flows to reduce the potential for roadway flooding during storm events, and to provide flood protection for the existing structures and residences within the Project area by improving drainage.
Following Board approval of this item, construction is anticipated to commence November 2023 and be completed by April 2024.
PROCUREMENT
This Project was advertised in the Daily Press newspaper on August 3, 2023, in the Precinct Reporter on August 3, 2023, and released on the County Electronic Procurement Network (ePro) on August 3, 2023. Notice inviting bids was also provided to specified construction trade journals as required by Public Contract Code section 22036. On September 21, 2023, the following five bids were received:
|
Contractor |
Location |
Total Bid |
|
H&H General Contractors, Inc. |
Highland, CA |
$1,913,205 |
|
EverLevel Holdings, LLC |
Chino Hills, CA |
$1,945,955 |
|
Granite Construction Company |
Indio, CA |
$2,757,572 |
|
Riverside Construction |
Riverside, CA |
$2,792,110 |
|
Metro Builders & Engineers Group, Ltd. |
Newport Beach, CA |
$3,680,394 |
There were three addendums issued during the bidding phase.
Addendum No. 1: Amended the bid opening date.
Addendum No. 2: Amended the bid opening time, the Special Provisions, Supplemental Work; replace Paragraph 8 for Remove, Stockpile and Reuse Existing Rock Slope Protection; replaced bid sheets; replaced 2018 Caltrans Standard Plan D86A; and answered questions.
Addendum No. 3: Amended the bid opening time.
The District reviewed the bids received and determined that they are responsive and recommends that the Board award the contract to H&H General Contractors, Inc., the lowest responsive bidder. No appeal/protest letters were received.
This Project will have a 10 percent contingency fund of $191,320 to compensate the contractor for verified quantity overruns, as well as changes in the contract under certain circumstances. Under an established formula based on the contract amount, Public Contract Code section 21061(d) allows the Board to authorize the Chief Flood Control Engineer to order changes in the contract, including for unforeseen conditions or design shortfalls, should they become necessary in the future, for a total amount not to exceed $108,160 of the $191,320 contingency fund.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Sophie A. Curtis, Deputy County Counsel, 387-5455) on September 27, 2023; Purchasing (Jason Cloninger, Lead Buyer, 387-8258) on September 27, 2023; Finance (Carl Lofton, Administrative Analyst, 387-5404) on October 4, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on October 6, 2023.