Subject: Amendment to Contract with Biggs Cardosa Associates, Inc. for Glen Helen Parkway Bridge over Cajon Wash, Devore Area
Attachments: 1. ADD-CON-PW-Trans 12-15-20 Amend Con with Biggs Cardosa Associates for Glen Helen Parkway Bridge, 2. ADD-EXH-PW-Trans 12-15-20 Amend Con with Biggs Cardosa Associates for Glen Helen Parkway Bridge - Exhibit B, Fee Proposal, 3. ADD-EXH-PW-Trans 12-15-20 Amend Con with Biggs Cardosa Associates for Glen Helen Parkway Bridge -Exhibit A-1, Scope of Services, 4. ADD-EXH-PW-Trans 12-15-20 Amend Con with Biggs Cardosa Associates for Glen Helen Parkway Bridge -Exhibit C, Schedule, 5. ADD-MAP-PW-Trans 12-15-20 Amend Con with Biggs Cardosa Associates for Glen Helen Parkway Bridge, 6. Item #58 Executed BAI, 7. 14-857-A-2 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

December 15, 2020

 

FROM

BRENDON BIGGS, Director, Department of Public Works - Transportation

 

SUBJECT

Title

Amendment to Contract with Biggs Cardosa Associates, Inc. for Glen Helen Parkway Bridge over Cajon Wash, Devore Area

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve Amendment No. 2 to Agreement No. 14-857 with Biggs Cardosa Associates, Inc. increasing the contract amount by $210,378 (from $1,599,963 to $1,810,341) for additional design and environmental services, extending the expiration date from December 30, 2020 to December 30, 2023, and incorporating all applicable required Caltrans terms and conditions for the bridge replacement project on Glen Helen Parkway over the Cajon Wash, in the Devore area (Project).

2.                     Authorize the Director of the Department of Public Works to reallocate funds between tasks in Contract No. 14-857, as modified by Amendment No. 2, as may be required to complete the Project work outlined in the agreement.

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost).  The Department of Public Works (Department) is funded by Gas Tax revenues, fees and other state and local funding. Costs associated with the Project are funded by the federal Highway Bridge Program at 88.53% ($1,602,695), and the County match of 11.47% ($207,646) is funded with Discretionary General Funding allocated in prior year Road Operation’s budgets. Sufficient appropriation and revenue are included in the Department’s 2020-21 Road Operations budget (6650002000 11H14646).

 

BACKGROUND INFORMATION

Project improvements include construction of a four-lane bridge over Cajon Wash with a transition to the grade separation crossing the Union Pacific and Burlington Northern Santa Fe railroad lines.  Construction of the Project will affect Glen Helen Regional Park (Park) property and during the design phase it was determined the Project requires the acquisition of additional road right-of-way through the Park.  The Department is working with State and Federal offices to perfect the right-of-way; however, this task has delayed the project for several years.  The acquisition of the additional road right-of-way through the Park, as required for the Project, cannot proceed until the existing public road right-of-way through the entirety of the Park has been perfected following the procedures administered by the State and Federal offices. 

 

The Department has also been coordinating with the U. S. Army Corps of Engineers (Corps) for the appropriate Section 408 approval required for the Project relating to alterations of the Corps’ Upper Devore Levee in the Cajon Wash; however, the Corps has not yet granted final Section 408 approval.

 

On October 21, 2014 (Item No. 35), the Board of Supervisors (Board) approved Contract No. 14-857 with Biggs Cardosa Associates, Inc. (BCA) for $1,599,963 to provide professional engineering and environmental services for the Project, and on December 5, 2017 (Item No. 44) the Board approved Amendment No.1 to Contract No. 14-857 extending the term of the contract to December 30, 2020, with no change in the contact amount.

 

Right-of-way acquisitions and Corps Section 408 approval have caused significant delays to the Project resulting in the need to design drainage revisions and revalidate previously issued environmental permits that have expired.  To date, BCA has submitted 95% plans; however, once the right-of-way is perfected and the Department has obtained Corps final approval, drainage design revisions and permit revalidations will be required.   Amendment No. 2 will allow BCA to proceed with revising drainage plans to meet Corps approval, finalizing all plans, specifications and estimates and revising the Habitat Enhancement Plan/Habitat Mitigation and Monitoring Plan.  Amendment No. 2 also provides the optional tasks of revalidating environmental permits and performing California Endangered Species Act Consultation should either be required.  BCA will utilize the remaining balances of various tasks in the existing budget, in conjunction with these additional funds to complete the design.  In addition, the amendment updates the contract schedule as both the Department and BCA agree that additional time is necessary to perfect the right-of-way, complete these services and allows the Department to reallocate funds between tasks, if necessary.

 

The Project meets the County and Chief Executive Officer’s goals and objectives to ensure development of a well-planned, balanced and sustainable County and by providing for the safety, health and social services needs of County residents by improving Glen Helen Parkway.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Scott M. Runyan, Deputy County Counsel, 387-5455) on November 19, 2020; Finance (Jessica Trillo, Administrative Analyst, 387-4222) on November 25, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on November 29, 2020.