Legislation Details

File #: 7533   
Type: Consent Status: Passed
File created: 2/17/2023 Department: Real Estate Services
On agenda: 2/28/2023 Final action: 2/28/2023
Subject: Amendment Template to Extend Temporary Construction Easements for the 40th Street and Other Americans with Disabilities Act Improvement Project in the Unincorporated Arrowhead Farms Area
Attachments: 1. MAP-RESD-DPW-022823-Appraisal and Acquisition TCE Extensions, 2. ADD-ATT-RESD-DPW-022823-Appraisal and Acquisition TCE Extensions, 3. Item #58 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

February 28, 2023

 

FROM

TERRY W. THOMPSON, Director, Real Estate Services Department

BRENDON BIGGS, Director, Department of Public Works - Transportation

         

SUBJECT                      

Title                     

Amendment Template to Extend Temporary Construction Easements for the 40th Street and Other Americans with Disabilities Act Improvement Project in the Unincorporated Arrowhead Farms Area

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve Amendment No. 1 to the Acquisition Agreement and Escrow Instructions template, with Temporary Construction Easements, for use with 18 property ownership groups, to extend the terms of 18 Temporary Construction Easements for one year, beginning March 1, 2023 and terminating February 29, 2024.

2.                     Authorize the Director of the Real Estate Services Department to execute Amendment No. 1 to the Acquisition Agreement and Escrow Instructions template with 18 property ownership groups, including the Temporary Construction Easements, and any other documents necessary to complete these transactions, subject to County Counsel review.

(Presenter: Terry W. Thompson, Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost).  The Department of Public Works - Transportation (DPW-T) is funded by Gas Tax revenues, fee revenue, and other state and local funding.  The total cost to extend 18 Temporary Construction Easements (TCE) is estimated to be $9,018.  Sufficient appropriation and revenue are included in DPW-T 2022-23 Road Operations budgets (6650002000 34H14922 and 20H14924) and will be included in 2023-24 recommended budgets.

 

BACKGROUND INFORMATION

On May 10, 2022 (Item No. 45), the Board of Supervisors (Board) approved the acquisition of 12 Permanent Roadway Easements and 22 TCE’s on portions of 23 parcels (Assessor Parcel Numbers (APNs) provided in the table below) through February 28, 2023, from 22 property ownership groups for the 40th Street and Other Americans with Disabilities Act Improvement Project (Project) in the unincorporated area of San Bernardino County (County) known as Arrowhead Farms. The Board also approved the Acquisition Agreement and Escrow Instructions template for the easement interests with the 22 property ownership groups. 

 

The Project involves installing new or reconstructing existing curb ramps at various locations in the north San Bernardino area known as Arrowhead Farms on 40th Street, 41st Street, 48th Street, Reservoir Drive and Hill Drive, in accordance with current design standards and pursuant to the Americans with Disabilities Act (ADA).

 

DPW-T requested the Real Estate Services Department (RESD) assist with the acquisition.  RESD obtained 18 executed TCE’s and 9 executed easements from the 22 property ownership groups.  A TCE provides working space and allows DPW to enter private property, for a specified time frame, in order to complete the improvements associated with the Project, while an easement is an acquired perpetual right for the specific use of land owned by others. 

 

As the expiration of the initial terms of the executed TCE’s approached, it became clear that construction of the Project would be delayed as the construction contract award and beginning of construction would occur until after the Winter of 2022-23.  Due to the delay, one-year extensions of 18 of the 22 TCE’s, originally approved by the Board, would be needed in order to meet construction deadlines.  The remaining 4 TCE’s, out of the 22 total, have been moved to another project.

 

Appraisal Nos. 22-01 through 22-23, copies of which are on file with RESD and were professionally reviewed and approved by qualified RESD staff, establish the amounts of additional compensation to be paid to the 18 property owners for one-year extensions of the TCE’s necessary to construct the Project.  The total cost to extend 18 TCE’s is estimated to be $9,018.  RESD recommends the additional compensation for the extensions be approved.  TCE’s will be extended for the following property ownership groups:

 

 Property Owner/Last Name

Exhibit No. and Type of Easement

 APN

Total Area to be Acquired (square feet)

Huerta

TCE-1 (Temporary)

0265-101-05

114

KN Homes, LLC

TCE-2 (Temporary)

0265-121-17

167

Neighbors

TCE-7 (Temporary)

0265-151-61

410

Vega

TCE-8 (Temporary)

0265-161-35

200

Chi

TCE-10 (Temporary)

0265-171-18

350

Casarez

TCE-11 (Temporary)

0265-171-43

167

Santiago Cordova

TCE-14 (Temporary)

0265-181-30

174

Vargas-Nunez

TCE-16 (Temporary)

0265-151-43

114

Donna J. Stager

TCE-18 (Temporary)

0265-161-51

181

Centeno

TCE-19 (Temporary)

0265-171-09

181

Cobra 28 No. 8, LP

TCE-20 (Temporary)

0265-241-47

110

Wingo

TCE-21 (Temporary)

0265-171-26

216

Nahas

TCE-22 (Temporary)

0265-241-02

238

Jay Revocable Living Trust

TCE-23 (Temporary)

0265-241-20

167

Kase / Herzberg

TCE-24 (Temporary)

0265-251-20

137

French

TCE-25 (Temporary)

0265-271-27

254

Machinery Manufacturer LLC

TCE-26 (Temporary)

0265-271-14

209

French

TCE-27 (Temporary)

0265-272-12

  46

 

On September 15, 2020 (Item No. 49), the Board approved the Project and considered a categorical exemption in accordance with the California Environmental Quality Act (CEQA).  The Clerk of the Board was directed to file and post a Notice of Exemption.  Accordingly, no further action is required under CEQA.

 

If approved, the Director of RESD will be able to execute Amendment No. 1 to the Acquisition Agreement and Escrow Instructions template, including the TCEs, to extend the terms of 18 TCEs.

 

PROCUREMENT

The County can amend the Acquisition Agreements and Escrow Instructions, and extend the terms of the TCE’s, in conformance with all applicable provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, as amended, Government Code section 7260 et seq., corresponding regulations, and County Policy No. 12-20 County Acquisition & Relocation Policy, to encourage and expedite the acquisition of real property by agreements with owners, to avoid litigation over such acquisitions, to assure fair and consistent treatment for owners whose real property is necessary for public programs, and to promote public confidence in the land acquisition practices of the County.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (John Tubbs II, Deputy County Counsel, and Aaron Gest, Deputy County Counsel, 387-5455) on February 15, 2023; Public Works - Transportation (Mervat Mikhail, Deputy Director, 387-7916) on January 25, 2023; Purchasing (Michelle Churchill, Supervising Buyer, 387-2070) on January 26, 2023; Finance (Carl Lofton, Administrative Analyst, 387-5404 and Penelope Chang, Administrative Analyst, 387-5423) on February 9, 2023; and County Finance and Administration (Valerie Clay, Deputy Executive Officer, 387-5423) on February 9, 2023.

 

(JAG:677-8210)