REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
January 28, 2020
FROM
BEAHTA R. DAVIS, Director, Regional Parks Department
TERRY W. THOMPSON, Director, Real Estate Services Department
SUBJECT
Title
Budget Adjustments for Glen Helen Amphitheater HVAC Project
End
RECOMMENDATION(S)
Recommendation
1. Approve a $32,000 increase in the project budget from $132,000 to $164,000 for the Glen Helen Amphitheater HVAC Replacement Project (CIP 20-117/WBSE 10.10.0938) located at 2555 Glen Helen Parkway in San Bernardino
2. Authorize the Auditor-Controller/Treasure/Tax Collector to post the necessary budget adjustments, as detailed in the Financial Impact Section. (Four votes required).
(Presenter: Beahta R. Davis, Director, 387-2340)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
Provide for the Safety, Health and Social Service Needs of County Residents.
Pursue County Goals and Objectives by Working with Other Agencies.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). Regional Parks Department (Department) will fund the $32,000 increase to the project budget for the Glen Helen Amphitheater HVAC Replacement Project with the Use of Fund Balance from Regional Parks’ Amphitheater Improvements at Glen Helen Regional Park Special Revenue Fund (Fund 2732).
|
Fund Center |
Commitment Item/GL Account |
Description |
Action |
Amount |
WBSE |
|
6520002732 |
55305030 |
Operating Transfers Out |
Increase |
$32,000 |
|
|
6520002732 |
37008880 |
F/B Res - Available Reserves |
Decrease |
$32,000 |
|
|
7700003100 |
40909975 |
Operating Transfers In |
Increase |
$32,000 |
10.10.0938 |
|
7700003100 |
54304030 |
Improvements to Structure |
Increase |
$32,000 |
10.10.0938 |
BACKGROUND INFORMATION
On August 20, 2019 (Item No. 57), the Board of Supervisors approved the HVAC Replacement Project at Glen Helen Amphitheater using the Amphitheater Improvement fund. After detailed review and investigation by the Project Management Division (PMD), it was determined the project needs a budget increase in the amount of $32,000. Based on additional information from several on-site walks, the scope of work and additional construction costs required for replacement of the existing HVAC units and electrical connections is greater than anticipated. The requested budget adjustment will increase the project budget from $132,000 to $164,000.
PROCUREMENT
N/A
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Dawn Martin, Deputy County Counsel, 387-4322) on December 23, 2019; Auditor-Controller/Treasurer/Tax Collector (Lisa Lazzar, General Accounting Manager, 382-3196) on December 23, 2019; Real Estate Services Department- Project Management Division (Darlynn Wissert, Deputy Director, 909-387-5000) on January 10, 2020; Finance (Elias Duenas, Administrative Analyst, 387-4052) on January 10, 2020, and (Wen Mai, Principal Administrative Analyst, 387-4883) on January 10, 2020; and County Finance and Administration (Robert Saldana, Deputy Executive Officer, 387-5423) on January 13, 2020.