File #: 12917   
Type: Consent Status: Passed
File created: 9/15/2025 Department: Public Works-Transportation
On agenda: 9/23/2025 Final action: 9/23/2025
Subject: Contract with DT Stellar General Engineering for the South Fontana Americans with Disabilities Act Ramps Project - Phase 1 in the South Fontana Area
Attachments: 1. CON-PW-Trans 9-23-25 con with DT Stellar General Engineering for South Fontana ADA Ramps South Fontana area_v4, 2. MAP-PW-Trans-9-23-25 PS South Fontana Area ADA Ramps
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

September 23, 2025

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Contract with DT Stellar General Engineering for the South Fontana Americans with Disabilities Act Ramps Project - Phase 1 in the South Fontana Area
End

RECOMMENDATION(S)
Recommendation
1. Award construction contract to DT Stellar General Engineering, in the amount of $557,819, for the South Fontana Americans with Disabilities Act Ramps Project - Phase 1 in the South Fontana area.
2. Authorize a contingency fund of $55,781 for the South Fontana Americans with Disabilities Act Ramps Project - Phase 1 in the South Fontana area.
3. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $55,781 for verified quantity overruns for this unit priced construction contract.
4. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $40,390 of the $55,781 contingency fund, pursuant to Public Contract Code Section 20142.
5. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Byanka Velasco, Assistant Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The South Fontana Americans with Disabilities Act Ramps Project - Phase 1 in the South Fontana area (Project) is funded with grant revenue from the Community Development Block Grant (CDBG) funds administered by the San Bernardino County Community Dev...