REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
November 5, 2024
FROM
DON DAY, Director, Project and Facilities Management Department
LYNN FYHRLUND, Chief Information Officer, Innovation and Technology Department
SUBJECT
Title
Amendment to Construction Contract with Rasmussen Brothers Construction, Inc. for the 800MHz Upgrades Cajon Pass Tower Project in Cajon Pass
End
RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Contract No. 23-1111 with Rasmussen Brothers Construction, Inc. in the amount of $35,949, increasing the contract from $807,938.14 to a total of $843,887.14, and extending the construction completion date from December 19, 2024, to February 28, 2025, for the 800MHz Upgrades Cajon Pass Tower Project (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item does not require additional Discretionary General Funding (Net County Cost). The 800MHz Upgrades Cajon Pass Tower Project (WBSE 10.10.1011) budget of $1,409,412 is comprised of the following components:
Description
Amount
Project Design
$ 199,048.00
Project Management, Inspection and Testing
$ 243,604.00
Construction
$ 843,887.14
Construction Contingency
$ 46,241.86
Project Contingency
$ 76,631.00
Total Project Budget
$ 1,409,412.00
There are sufficient funds in the project contingency to fund the additional cost of this amendment.
BACKGROUND INFORMATION
The Project and Facilities Management Department (PFMD) is constructing a radio communications site in a United States Forest Service leased Project site located at the top of the Cajon Pass, between the north and southbound lanes of the I-15 freeway. The project scope includes the construction of a new 264 square-foot structure that houses ...
Click here for full text