Subject: Contract with Calmex Engineering, Inc. for the Pipeline Avenue and Other Roads Project in the Chino and Montclair Areas
Attachments: 1. ATT-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area, Attachment C ARPA, 2. ATT-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area, FHWA 1273, 3. ATT-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area, Attachment D, 4. ATT-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area, Addendum No. 1 (2), 5. ATT-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area, Addendum No. 2 (1), 6. MAP-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area, 7. R2-CON-PW-Trans 11-19-24 Con with Calmex Engineering for Pipeline Ave. and Other Roads, Chino Area (1), 8. Item #50 Executed BAI, 9. 24-1088 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

November 19, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Contract with Calmex Engineering, Inc. for the Pipeline Avenue and Other Roads Project in the Chino and Montclair Areas
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No 1, issued on September 4, 2024, and Addendum No. 2, issued on September 27, 2024, to the bid documents for the Pipeline Avenue and Other Roads Project in the Chino and Montclair areas.
2. Award a construction contract to Calmex Engineering, Inc. (Bloomington, CA) in the amount of $6,177,899.11 for the Pipeline Avenue and Other Roads Project in the Chino and Montclair areas.
3. Authorize a contingency fund of $617,789 for the Pipeline Avenue and Other Roads Project in the Chino and Montclair areas.
4. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $617,789 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $210,000 of the $617,789 contingency fund, pursuant to Public Contract Code section 20142.
6. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
7. Approve the use of up to $450,000 of American Rescue Plan Act Coronavirus Local Fiscal Recovery Fund Program funding for eligible costs for the Pipeline Avenue and Other Roads Project in the Chino and Montclair areas.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
Pursue...