REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
October 24, 2023
FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation
SUBJECT
Title
California Environmental Quality Act Finding for the Mountain Drive and 4th Avenue Project in the Arrowhead Farms Area
End
RECOMMENDATION(S)
Recommendation
1. Find that the Mountain Drive and 4th Avenue Project in the Arrowhead Farms area is exempt under the California Environmental Quality Act, Title 14 of the California Code of Regulations Section 15301(a) Class 1 (alterations of existing facilities) and Section 15302(c) Class 2 (replacement or reconstruction of existing structures or facilities).
2. Approve the Mountain Drive and 4th Avenue Project in the Arrowhead Farms area, as defined in the Notice of Exemption.
3. Direct the Clerk of the Board of Supervisors to file and post the Notice of Exemption.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The channel improvements element for the Mountain Drive and 4th Avenue Project in the Arrowhead Farms area (Project) will be funded by the San Bernardino County Flood Control District (District) with property tax revenue. The road improvements element of the Project will be funded by the City of San Bernardino (City) with Gas Tax funds administered by the Department of Public Works (Department), and Senate Bill 1 (SB 1) Road Maintenance and Rehabilitation Account (RMRA) funds. Sufficient appropriation and revenue for the Project have been included in the District’s 2023-24 budget (1920002522 F02843) as well as the Department’s 2023-24 Road Operations budget (6650002000 H15123) and will be included in future recommended budgets.
BACKGROUND INFORMATION
The Project consists of replacing the existing two-lane low water crossings both on Mountain Drive at Devil Creek Channel and 4th Avenue at Devil Creek Channel, with a quadruple reinforced concrete box at each location to improve the capacity and conveyance of the District maintained facility to meet the calculated 100-year peak storm flows. The Project also includes roadway improvements consisting of pavement rehabilitation and Americans with Disabilities Act (ADA) curb ramp updates on 4th Avenue, from Kendall Drive north 0.08 miles and on Mountain Drive, from Kendall Drive north 0.08 miles. This element of the Project was prioritized by the Board of Supervisors (Board) as part of the 2022-23 SB 1 RMRA project list, which was approved on May 24, 2022 (Item No. 87).
On July 25, 2023 (Item No. 49), the Board approved Cooperative Agreement No. 23-825 between the County and the City for the implementation of this Project’s road reconstruction and ADA curb ramps. The agreement terminates upon completion of the Project and payment by the City, or on December 21, 2026, whichever occurs first.
On August 17, 2023, the County’s environmental staff reviewed this Project and identified two categorical exemptions applicable to the Project under California Environmental Quality Act (CEQA) Guidelines, Title 14 of the California Code Regulations, Section 15301 (c) Class 1 and Section 15302(c) Class 2. The Class 1 exemption allows for minor alteration of existing public or private structures. The Class 2 exemption allows for the replacement or reconstruction of existing structures or facilities where the new structure will be located on the same site as the structure replaced and will have substantially the same purpose and capacity as the structure replaced. When the Board considers the environmental finding, the filing and posting of a Notice of Exemption is recommended.
The Department anticipates presenting a cooperative agreement between the County and the District for implementation of the Project’s culvert construction to the Board for consideration in Winter 2023-24.
The Project is consistent with the County and the Chief Executive Officer’s goals and objectives to provide for the safety, health, and social service needs of County residents by conveying flows to reduce the potential for roadway flooding during storm events and to provide flood protection for the existing structures and residences within the Project area by improving drainage.
PROCUREMENT
The County anticipates presenting the Project’s plans and specifications, as well as a recommendation to advertise for formal bids, to the Board for consideration in Fall 2024.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on September 25, 2023; Finance (Carl Lofton, Administrative Analyst, 387-5404) on October 4, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on October 6, 2023.