File #: 10562   
Type: Consent Status: Passed
File created: 7/16/2024 Department: Public Works-Transportation
On agenda: 7/23/2024 Final action: 7/23/2024
Subject: Project Funding Agreement with the San Bernardino County Transportation Authority for the National Trails Highway Bridge Replacement Project
Attachments: 1. COV-PW-Trans 7-23-24 Project Funding Agr with the San Bernardino County Transportation Authority for the National Trails Highway Bridge Replacement Proj, 2. AGR-PW-Trans 7-23-24 Project Funding Agr with the San Bernardino County Transportation Authority for the National Trails Highway Bridge Replacement Proj Final, 3. MAP-PW-Trans 7-23-24 Project Funding Agr with the San Bernardino County Transportation Authority for the National Trails Highway Bridge Replacement Proj, 4. ADD-ATT-PW-Trans 7-23-24 Project Funding Agr with the San Bernardino County Transportation Authority for the National Trails Highway Bridge Replacement Proj
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

July 23, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Project Funding Agreement with the San Bernardino County Transportation Authority for the National Trails Highway Bridge Replacement Project
End

RECOMMENDATION(S)
Recommendation
1. Approve Project Funding Agreement (Agreement No. 24-1003172) with the San Bernardino County Transportation Authority, for bridge reconstructions on National Trails Highway, from the community of Dagget to Mountain Springs Road near Goffs area , effective upon execution by both parties until final reimbursement is received or June 30, 2032, whichever occurs first, to receive an amount not to exceed $61,004,382.
2. Authorize the Chief Executive Officer to execute a letter to authorize and approve nomination of the National Trails Highway bridges for an allocation of Local Partnership Program funding, in the amount of $5,776,000, under the Senate Bill 1 Local Partnership Program.
3. Direct the Director of the Department of Public Works to transmit the fully executed letter in Recommendation No. 2 to the Clerk of the Board of Supervisors within 30 days of execution.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). A total of $23,425,000 of Discretionary General Funding (DGF) was allocated in 2014-2015, 2015-2016, 2016-2017, and 2024-2025 to the Department of Public Works (Department) budgets for the National Trails Highway Bridge Replacement Project (Project). The estimated total cost for the Project under this Funding Agreement (Agreement No. 24-...