Subject: Amendment to Contract with Michael Baker International for the Lake Gregory Regional Park Sitewide Sediment Management Project
Attachments: 1. ADD-CON-PW-SD 032525 Lake Gregory Sitewide Sediment Contract Amendment No.pdf, 2. Item #44 Executed BAI, 3. 23-477 A-2 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

March 25, 2025

FROM
NOEL CASTILLO, Director, Department of Public Works - Special Districts
BEAHTA R. DAVIS, Director, Regional Parks Department

SUBJECT
Title
Amendment to Contract with Michael Baker International for the Lake Gregory Regional Park Sitewide Sediment Management Project
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 2 to Contract No. 23-477 with Michael Baker International for professional engineering design services associated with the Lake Gregory Regional Park Sitewide Sediment Management Project, increasing the total approved contract amount by $29,990, from $487,140 to $517,130, with no change to the contract term of May 23, 2023, through December 31, 2026.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). Reimbursement of eligible expenditures for the Lake Gregory Regional Park Sitewide Sediment Project (Project) was funded through an allocation of $1,765,000 from the County's American Rescue Plan Act (ARPA) Coronavirus Local Fiscal Recovery Fund (CLFRF) for eligible costs and a one-time Discretionary General Funding allocation for the Project of $3,235,000. The total combined allocation for the Project is $5,000,000.

Sufficient appropriation for the Project, including the proposed amendment, is included in the Department of Public Works - Special Districts' (Department) County Service Area (CSA) 70 - Countywide Capital Improvement Project's (CIP) 2024-25 budget and will be included in future recommended budgets as needed.

BACKGROUND INFORMATION
The Department provides des...