Subject: California Environmental Quality Act Finding and Specifications for the Ceres Avenue and Other Roads Project in the Fontana Area
Attachments: 1. ATT-PW-Trans 8-8-23 CEQA and Specs for Ceres Ave and Other Roads Project, Fontana Area - Specs 2 of 3, 2. MAP-PW-Trans 8-8-23 CEQA and Specs for Ceres Ave and Other Roads Project, Fontana Area, 3. ATT-PW-Trans 8-8-23 CEQA and Specs for Ceres Ave and Other Roads Project, Fontana Area - NOE, 4. ATT-PW-Trans 8-8-23 CEQA and Specs for Ceres Ave and Other Roads Project, Fontana Area - Specs 1 of 3, 5. ADD-ATT-PW-Trans 8-8-23 CEQA and Specs for Ceres Ave and Other Roads Project, Fontana Area - Specs 3 of 3, 6. Item #42 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 8, 2023

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
California Environmental Quality Act Finding and Specifications for the Ceres Avenue and Other Roads Project in the Fontana Area
End

RECOMMENDATION(S)
Recommendation
1. Find that the Ceres Avenue and Other Roads Project in the Fontana area is exempt under the California Environmental Quality Act Guidelines, Title 14 of the California Code of Regulations Section 15301(c) Class 1 (existing facilities) and Section 15302(c) Class 2 (replacement or reconstruction).
2. Approve the Ceres Avenue and Other Roads Project in the Fontana area as defined in the Notice of Exemption.
3. Approve specifications for the Ceres Avenue and Other Roads Project in the Fontana area, as signed and sealed by a registered civil engineer.
4. Authorize the Director of the Department of Public Works to advertise the Ceres Avenue and Other Roads Project in the Fontana area for formal bids.
5. Direct the Clerk of the Board of Supervisors to file and post the Notice of Exemption.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Ceres Avenue and Other Roads Project in the Fontana area (Project) will be funded with Senate Bill 1 (SB 1) Road Maintenance and Rehabilitation Account (RMRA) funds. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2023-24 Road Operations budget (6650002000 31H15155).

BACKGROUND INFORMATION
The Project involves pavement rehabilitation to approximately 19 miles of roads, sidewalks, curb and gut...

Click here for full text