File #: 13524   
Type: Consent Status: Passed
File created: 1/6/2026 Department: Project and Facilities Management
On agenda: 1/13/2026 Final action: 1/13/2026
Subject: Amendment and Change Order to Construction Contract with Angeles Contractor, Inc. for the Sheriff Colorado River Station Remodel Project
Attachments: 1. CON-PFMD-11326-Amendment-Change Order-Amendment-Angeles-SHR Colorado River Station Remodel Project, 2. CON-PFMD-11326-Amendment-Change Order-Change Order-Angeles-SHR Colorado River Station Remodel Project, 3. Item #41 Executed BAI, 4. 23-929 C-8 Executed Contract, 5. 23-929 A-5 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

January 13, 2026

FROM
DON DAY, Director, Project and Facilities Management Department
SHANNON D. DICUS, Sheriff/Coroner/Public Administrator

SUBJECT
Title
Amendment and Change Order to Construction Contract with Angeles Contractor, Inc. for the Sheriff Colorado River Station Remodel Project
End

End
RECOMMENDATION(S)
Recommendation
1. Approve Amendment No. 5 to Construction Contract No. 23-929 with Angeles Contractor, Inc., for the Sheriff Colorado River Station Remodel Project in Needles, increasing the contract amount by $744,556, from $10,685,059 to $11,429,615, and increasing construction time by 149 days, from 393 days to 542 days (Four votes required).
2. Approve Change Order No. 8 to Construction Contract No. 23-929 with Angeles Contractor, Inc., increasing the total amount by $44,411, from $11,429,615 to $11,474,026, and increasing construction time by 149 days, from 393 days to 542 days (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Sheriff/Coroner/Public Administrator's (Sheriff) Colorado River Station Remodel Project (Project) (WBSE 10.10.1220) budget of $13,952,484 is funded from Discretionary General Funding ($6,594,490) and Proposition 172 funds ($7,357,994), as part of the 2025-26 Capital Improvement Program (CIP) budget approved by the Board of Supervisors (Board) on June 10, 2025 (Item No. 136).

BACKGROUND INFORMATION
Approval of Amendment No. 5 (A5) to Construction Contract No....